In ExtensionP52100021371Registered Jun 2019Delayed 1015dExtension1 red flag

Ravinanda37

A commercial project by Ravinanda Icon Landmarks Unit1 in PARGE NAGAR, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
82%
cost-weighted
Declared completion
Mar 2027
delayed 1015d
Units sold
70 / 109
64% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Ravinanda Icon Landmarks Unit1 · Partnership
Project type
Commercial
Land area
8,043 m² · Permissible built-up (FSI) 16,000 m²
Total units
109 across 2 wings
Estimated cost
₹34.1 Cr
Land ownership
Promoter is the landowner
Held outside open sale
4 landowner/investor share
Application date
19 Jun 2019
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA8 of 8 proposed56
NA9 of 9 proposed53
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
GIRISH KAKANDE
Structural engineer
S K Consultants & Engineers · STATE/R/2024/APL/14306
Project bank
HDFC BANK
Location

Where it sits

PARGE NAGAR, Pune — 411048.

Locality
PARGE NAGAR
District
Pune
Authority
Pune Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Ravinanda37: common questions

Is Ravinanda37 RERA registered?

Yes. Ravinanda37 is registered with MahaRERA under registration number P52100021371, granted on 24 June 2019. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Ravinanda37?

The developer has declared completion by March 2027 in its MahaRERA filing, revised from the original June 2024. The record shows the project running 1015 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Ravinanda37?

Ravinanda37 is developed by Ravinanda Icon Landmarks Unit1, the promoter named in its MahaRERA registration.

Where is Ravinanda37 located?

Ravinanda37 is in Parge Nagar, Pune (PIN 411048), Maharashtra, as declared in its RERA registration.

How many units does Ravinanda37 have, and how many are sold?

Ravinanda37 has 109 units on its RERA registration. 70 were reported sold as of July 2026, leaving 39 unsold.

How much construction of Ravinanda37 is complete?

By the developer's own quarterly filing, 82% of the work is done, measured against the project's cost estimate.

Is there any litigation against Ravinanda37?

No litigation is declared on Ravinanda37's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Parge Nagar