Status & progress

Per MahaRERA record as of Sept 2026.

Construction
80%
cost-weighted
Declared completion
Dec 2026
delayed 1097d
Units sold
119 / 126
94% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Om Sai Developers · Partnership
Project type
Residential / Group Housing
Land area
4,600 m² · Permissible built-up (FSI) 10,267 m²
Total units
126 across 1 wing
Estimated cost
₹23 Cr
Land ownership
Promoter is the landowner
Application date
25 Apr 2018
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA13 of 13 proposed126
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Koppa Architecture & Design Consultants
Structural engineer
STRUTURE VISION
Project bank
THE COSMOS CO OPERATIVE BANK LIMITED
Location

Where it sits

Chavan Baugh, Pune — 411041.

Locality
Chavan Baugh
District
Pune
Authority
Pune Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Ravinanda Aamrai Phase 1 Building C: common questions

Is Ravinanda Aamrai Phase 1 Building C RERA registered?

Yes. Ravinanda Aamrai Phase 1 Building C is registered with MahaRERA under registration number P52100016536, granted on 21 May 2018. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Ravinanda Aamrai Phase 1 Building C?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2023. The record shows the project running 1097 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Ravinanda Aamrai Phase 1 Building C?

Ravinanda Aamrai Phase 1 Building C is developed by Om Sai Developers, the promoter named in its MahaRERA registration.

Where is Ravinanda Aamrai Phase 1 Building C located?

Ravinanda Aamrai Phase 1 Building C is in Chavan Baugh, Pune (PIN 411041), Maharashtra, as declared in its RERA registration.

How many units does Ravinanda Aamrai Phase 1 Building C have, and how many are sold?

Ravinanda Aamrai Phase 1 Building C has 126 units on its RERA registration. 119 were reported sold as of September 2026, leaving 7 unsold.

How much construction of Ravinanda Aamrai Phase 1 Building C is complete?

By the developer's own quarterly filing, 80% of the work is done, measured against the project's cost estimate.

Is there any litigation against Ravinanda Aamrai Phase 1 Building C?

No litigation is declared on Ravinanda Aamrai Phase 1 Building C's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.