In ExtensionP52100076854Registered Jul 2024Delayed 260dExtension1 red flag

Rahul Aston - II

A residential / group housing project by Rahul Construction in Hinjawadi, Pune.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
84%
cost-weighted
Declared completion
Dec 2026
delayed 260d
Units sold
157 / 217
72% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Rahul Construction · Partnership
Project type
Residential / Group Housing
Land area
3,180 m² · Permissible built-up (FSI) 24,031 m²
Total units
217 across 1 wing
Estimated cost
₹97 Cr
Land ownership
Promoter is the landowner
Parking
336 four-wheeler · 0 two-wheeler
Application date
05 Jan 2024
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA25 of 25 proposed217
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Pandit Joshi & Associates · CA/77/3917
Structural engineer
· Sr. No. B - 17 : 19940
Project bank
ICICI BANK LIMITED
Location

Where it sits

Hinjawadi, Pune — 411057.

Locality
Hinjawadi
District
Pune
Authority
PMRDA
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Rahul Aston - II: common questions

Is Rahul Aston - II RERA registered?

Yes. Rahul Aston - II is registered with MahaRERA under registration number P52100076854, granted on 3 July 2024. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Rahul Aston - II?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original April 2026. The record shows the project running 260 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Rahul Aston - II?

Rahul Aston - II is developed by Rahul Construction, the promoter named in its MahaRERA registration.

Where is Rahul Aston - II located?

Rahul Aston - II is in Hinjawadi, Pune (PIN 411057), Maharashtra, as declared in its RERA registration.

How many units does Rahul Aston - II have, and how many are sold?

Rahul Aston - II has 217 units on its RERA registration. 166 were reported sold as of September 2026, leaving 51 unsold.

How much construction of Rahul Aston - II is complete?

By the developer's own quarterly filing, 84% of the work is done, measured against the project's cost estimate.

Is there any litigation against Rahul Aston - II?

No litigation is declared on Rahul Aston - II's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Hinjawadi