In ExtensionP51900047226Registered Oct 2022Delayed 365dExtension1 red flag

Promesa Castor

A residential / group housing project by Darshan Group in khetwadi, Mumbai City.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
100%
cost-weighted
Declared completion
Dec 2026
delayed 365d
Units sold
0 / 104
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Darshan Group · Company
Project type
Residential / Group Housing
Land area
761 m² · Permissible built-up (FSI) 5,896 m²
Total units
104 across 1 wing
Estimated cost
₹18.3 Cr
Parking
57 four-wheeler · 0 two-wheeler
Held outside open sale
73 rehab
Application date
19 Sept 2022
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA24 of 24 proposed104
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Kaushal Chouhan · CA/99/24744
Structural engineer
Prakash Bajaj
Project bank
ICICI BANK LIMITED
Location

Where it sits

khetwadi, Mumbai City — 400004.

Locality
khetwadi
District
Mumbai City
Authority
CHE/CTY/1334/D/337(NEW)/IOD/1/AMEND
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Promesa Castor: common questions

Is Promesa Castor RERA registered?

Yes. Promesa Castor is registered with MahaRERA under registration number P51900047226, granted on 12 October 2022. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Promesa Castor?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Promesa Castor?

Promesa Castor is developed by Darshan Group, the promoter named in its MahaRERA registration.

Where is Promesa Castor located?

Promesa Castor is in Khetwadi, Mumbai (PIN 400004), Maharashtra, as declared in its RERA registration.

How many units does Promesa Castor have, and how many are sold?

Promesa Castor has 104 units on its RERA registration. 29 were reported sold as of September 2026, leaving 75 unsold.

How much construction of Promesa Castor is complete?

By the developer's own quarterly filing, 100% of the work is done, measured against the project's cost estimate.

Is there any litigation against Promesa Castor?

No litigation is declared on Promesa Castor's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.