In ExtensionP51800049682Registered Feb 2023Delayed 365dExtensionNo active red flags

Parleshwar Aangan

A others project by Panom Developers LLP in Vile Parle East, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
80%
cost-weighted
Declared completion
Dec 2026
delayed 365d
Units sold
49 / 240
20% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Panom Developers LLP · Partnership
Project type
Others
Land area
9,766 m² · Permissible built-up (FSI) 32,909 m²
Total units
240 across 3 wings
Estimated cost
₹74.9 Cr
Parking
103 four-wheeler · 0 two-wheeler
Held outside open sale
116 rehab
Application date
07 Dec 2022
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA14 of 14 proposed65
NA14 of 14 proposed51
NA12 of 12 proposed124
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Arch View Associates · 840004230
Structural engineer
Mr. Bhagwan Shivaram Ingole
Project bank
STATE BANK OF INDIA
Location

Where it sits

Vile Parle East, Mumbai Suburban — 400069.

Locality
Vile Parle East
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Parleshwar Aangan: common questions

Is Parleshwar Aangan RERA registered?

Yes. Parleshwar Aangan is registered with MahaRERA under registration number P51800049682, granted on 22 February 2023. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Parleshwar Aangan?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Parleshwar Aangan?

Parleshwar Aangan is developed by Panom Developers LLP, the promoter named in its MahaRERA registration.

Where is Parleshwar Aangan located?

Parleshwar Aangan is in Vile Parle East, Mumbai (PIN 400069), Maharashtra, as declared in its RERA registration.

How many units does Parleshwar Aangan have, and how many are sold?

Parleshwar Aangan has 240 units on its RERA registration. 49 were reported sold as of September 2026, leaving 191 unsold.

How much construction of Parleshwar Aangan is complete?

By the developer's own quarterly filing, 80% of the work is done, measured against the project's cost estimate.

Is there any litigation against Parleshwar Aangan?

2 litigation cases are declared on Parleshwar Aangan's MahaRERA record. The full report lists each case with its court and status.