In ExtensionP51800001904Registered Jul 2017Delayed 2741dExtension3 red flags

Parinee i

A commercial project by Parinee Realty Private Limited in Andheri west, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
117%
cost-weighted
Declared completion
Dec 2028
delayed 2741d
Units sold
216 / 286
76% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Parinee Realty Private Limited · Company
Project type
Commercial
Land area
3,997 m² · Permissible built-up (FSI) 17,454 m²
Total units
286 across 1 wing
Estimated cost
₹257.9 Cr
Application date
25 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA34 of 34 proposed286
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/98/23799
Structural engineer
Project bank
YES BANK
Location

Where it sits

Andheri west, Mumbai Suburban — 400053.

Locality
Andheri west
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority
Red flags

3 flags on this project

What they are and why they matter — in the full report.

Unlock the 3 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Parinee i: common questions

Is Parinee i RERA registered?

Yes. Parinee i is registered with MahaRERA under registration number P51800001904, granted on 29 July 2017. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Parinee i?

The developer has declared completion by December 2028 in its MahaRERA filing, revised from the original June 2021. The record shows the project running 2741 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Parinee i?

Parinee i is developed by Parinee Realty Private Limited, the promoter named in its MahaRERA registration.

Where is Parinee i located?

Parinee i is in Andheri West, Mumbai (PIN 400053), Maharashtra, as declared in its RERA registration.

How many units does Parinee i have, and how many are sold?

Parinee i has 286 units on its RERA registration. 246 were reported sold as of September 2026, leaving 40 unsold.

How much construction of Parinee i is complete?

By the developer's own quarterly filing, 117% of the work is done, measured against the project's cost estimate.

Is there any litigation against Parinee i?

1 litigation case is declared on Parinee i's MahaRERA record. The full report lists each case with its court and status.