In ExtensionP51700080793Registered Jul 2025Delayed 366dExtension1 red flag

OZONE GALAXY Phase III

A residential / group housing project by Hallmark Infra Realty LLP in OZONE GALAXY NEAR YOGESHWAR BUNGLOW, Thane.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
17%
cost-weighted
Declared completion
Dec 2026
delayed 366d
Units sold
19 / 76
25% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Hallmark Infra Realty LLP · Partnership
Project type
Residential / Group Housing
Land area
4,273 m² · Permissible built-up (FSI) 4,273 m²
Total units
76 across 2 wings
Estimated cost
₹21.1 Cr
Parking
24 four-wheeler · 0 two-wheeler
Application date
12 Feb 2025
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA9 of 9 proposed34
NA9 of 9 proposed42
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Atul Anil Gharat · STATE/R/2025/APL/15593
Structural engineer
Aditya Rajan Deshmukh · STATE/R/2023/APL/05005
Project bank
G P PARSIK BANK
Location

Where it sits

OZONE GALAXY NEAR YOGESHWAR BUNGLOW, Thane — 421302.

Locality
OZONE GALAXY NEAR YOGESHWAR BUNGLOW
District
Thane
Authority
Mumbai Metropolitan Region Development Authority
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

OZONE GALAXY Phase III: common questions

Is OZONE GALAXY Phase III RERA registered?

Yes. OZONE GALAXY Phase III is registered with MahaRERA under registration number P51700080793, granted on 8 July 2025. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of OZONE GALAXY Phase III?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 366 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of OZONE GALAXY Phase III?

OZONE GALAXY Phase III is developed by Hallmark Infra Realty LLP, the promoter named in its MahaRERA registration.

Where is OZONE GALAXY Phase III located?

OZONE GALAXY Phase III is in Thane (PIN 421302), Maharashtra, as declared in its RERA registration.

How many units does OZONE GALAXY Phase III have, and how many are sold?

OZONE GALAXY Phase III has 76 units on its RERA registration. 19 were reported sold as of September 2026, leaving 57 unsold.

How much construction of OZONE GALAXY Phase III is complete?

By the developer's own quarterly filing, 17% of the work is done, measured against the project's cost estimate.

Is there any litigation against OZONE GALAXY Phase III?

No litigation is declared on OZONE GALAXY Phase III's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

RERA projects nearby