ActiveP51800056047Registered May 20241 red flag

Origin Claremont

A residential / group housing project by Mpire Reality Limited in KANYAPADA DINDOSHI, Mumbai Suburban.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
4%
cost-weighted
Declared completion
Dec 2030
no delay on record
Units sold
29 / 152
19% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Mpire Reality Limited
Project type
Residential / Group Housing
Land area
1,254 m² · Permissible built-up (FSI) 17,500 m²
Total units
152 across 1 wing
Estimated cost
₹217.8 Cr
Land ownership
Promoter is the landowner
Parking
201 four-wheeler · 0 two-wheeler
Held outside open sale
5 reserved
Application date
12 Mar 2024
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA13 of 13 proposed152
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
DESIGN CONCEPTS · K/386/LS
Structural engineer
SUBHASH SINGH
Project bank
IDFC First Bank Ltd
Location

Where it sits

KANYAPADA DINDOSHI, Mumbai Suburban — 400063.

Locality
KANYAPADA DINDOSHI
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Origin Claremont: common questions

Is Origin Claremont RERA registered?

Yes. Origin Claremont is registered with MahaRERA under registration number P51800056047, granted on 10 May 2024. As of July 2026, the registration is active.

What is the possession date of Origin Claremont?

The developer has declared completion by December 2030 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Origin Claremont?

Origin Claremont is developed by Mpire Reality Limited, the promoter named in its MahaRERA registration.

Where is Origin Claremont located?

Origin Claremont is in Kanyapada Dindoshi, Mumbai (PIN 400063), Maharashtra, as declared in its RERA registration.

How many units does Origin Claremont have, and how many are sold?

Origin Claremont has 152 units on its RERA registration. 29 were reported sold as of July 2026, leaving 123 unsold.

How much construction of Origin Claremont is complete?

By the developer's own quarterly filing, 4% of the work is done, measured against the project's cost estimate.

Is there any litigation against Origin Claremont?

No litigation is declared on Origin Claremont's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.