Om Mangalam Yash
A others project by Shri Associates in VILLEGE KIWALE, Pune.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Shri Associates · Others
- Project type
- Others
- Land area
- 8,206 m² · Permissible built-up (FSI) 20,660 m²
- Total units
- 229 across 2 wings
- Estimated cost
- ₹74 Cr
- Parking
- 258 four-wheeler · 0 two-wheeler
- Application date
- 23 Mar 2022
2 wings
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 16 of 16 proposed | 112 |
| NA | 4 of 4 proposed | 117 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- SANKALP DESIGNER · PCMC/658/24
- Structural engineer
- VIJAY GAVADE · SE/086/2024
- Project bank
- INDUSIND BANK
Where it sits
VILLEGE KIWALE, Pune — 412101.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Om Mangalam Yash: common questions
Is Om Mangalam Yash RERA registered?
Yes. Om Mangalam Yash is registered with MahaRERA under registration number P52100034227, granted on 25 March 2022. As of July 2026, the registration is active.
What is the possession date of Om Mangalam Yash?
The developer has declared completion by December 2026 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Om Mangalam Yash?
Om Mangalam Yash is developed by Shri Associates, the promoter named in its MahaRERA registration.
Where is Om Mangalam Yash located?
Om Mangalam Yash is in Villege Kiwale, Pune (PIN 412101), Maharashtra, as declared in its RERA registration.
How many units does Om Mangalam Yash have, and how many are sold?
Om Mangalam Yash has 229 units on its RERA registration. 221 were reported sold as of July 2026, leaving 8 unsold.
How much construction of Om Mangalam Yash is complete?
By the developer's own quarterly filing, 99% of the work is done, measured against the project's cost estimate.
Is there any litigation against Om Mangalam Yash?
No litigation is declared on Om Mangalam Yash's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
RERA projects nearby
- Parvatara Phase 2 · Pune
- Samruddhi Nilaya · Pune
- VAASTU IMPERIAL Wing B · Pune
- VAASTU IMPERIAL Wing A · Pune