Status & progress

Per MahaRERA record as of Jul 2026.

Construction
40%
cost-weighted
Declared completion
May 2027
no delay on record
Units sold
580 / 727
80% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Nyati Builders Private Limited · Company
Project type
Others
Land area
60,606 m² · Permissible built-up (FSI) 85,487 m²
Total units
727 across 7 wings
Estimated cost
₹460.1 Cr
Parking
568 four-wheeler · 835 two-wheeler
Application date
10 May 2023
Buildings & units

7 wings across 7 buildings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA31 of 31 proposed122
NA31 of 31 proposed122
NA31 of 31 proposed123
NA31 of 31 proposed118
NA31 of 31 proposed118
NA31 of 31 proposed118
NA3 of 3 proposed6
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/89/12285
Structural engineer
JW Consultants LLP · PMC Lic NO - 20
Project bank
HDFC BANK
Location

Where it sits

BANER, Pune — 411045.

Locality
BANER
District
Pune
Authority
Pune Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Nyati Emerald I: common questions

Is Nyati Emerald I RERA registered?

Yes. Nyati Emerald I is registered with MahaRERA under registration number P52100051235, granted on 8 June 2023. As of July 2026, the registration is active.

What is the possession date of Nyati Emerald I?

The developer has declared completion by May 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Nyati Emerald I?

Nyati Emerald I is developed by Nyati Builders Private Limited, the promoter named in its MahaRERA registration.

Where is Nyati Emerald I located?

Nyati Emerald I is in Baner, Pune (PIN 411045), Maharashtra, as declared in its RERA registration.

How many units does Nyati Emerald I have, and how many are sold?

Nyati Emerald I has 727 units on its RERA registration. 590 were reported sold as of July 2026, leaving 137 unsold.

How much construction of Nyati Emerald I is complete?

By the developer's own quarterly filing, 40% of the work is done, measured against the project's cost estimate.

Is there any litigation against Nyati Emerald I?

8 litigation cases are declared on Nyati Emerald I's MahaRERA record. The full report lists each case with its court and status.