In ExtensionP51900034207Registered Mar 2022Delayed 729dExtension1 red flag

Nine Reflex

A residential / group housing project by Reflex Projects LLP in DADAR NAIGAON, Mumbai City.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
84%
cost-weighted
Declared completion
Dec 2026
delayed 729d
Units sold
7 / 71
10% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Reflex Projects LLP · Partnership
Project type
Residential / Group Housing
Land area
605 m² · Permissible built-up (FSI) 3,219 m²
Total units
71 across 1 wing
Estimated cost
₹15.9 Cr
Land ownership
Promoter is the landowner
Parking
22 four-wheeler · 0 two-wheeler
Held outside open sale
42 rehab
Application date
12 Mar 2022
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA24 of 24 proposed71
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
KALPESH L SHAH
Structural engineer
DHAVAL GANDHI
Project bank
HDFC BANK
Location

Where it sits

DADAR NAIGAON, Mumbai City — 400014.

Locality
DADAR NAIGAON
District
Mumbai City
Authority
BRIHANMUMBAI MUNICIPAL CORPORATION
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Nine Reflex: common questions

Is Nine Reflex RERA registered?

Yes. Nine Reflex is registered with MahaRERA under registration number P51900034207, granted on 25 March 2022. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Nine Reflex?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2024. The record shows the project running 729 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Nine Reflex?

Nine Reflex is developed by Reflex Projects LLP, the promoter named in its MahaRERA registration.

Where is Nine Reflex located?

Nine Reflex is in Dadar Naigaon, Mumbai (PIN 400014), Maharashtra, as declared in its RERA registration.

How many units does Nine Reflex have, and how many are sold?

Nine Reflex has 71 units on its RERA registration. 7 were reported sold as of September 2026, leaving 64 unsold.

How much construction of Nine Reflex is complete?

By the developer's own quarterly filing, 84% of the work is done, measured against the project's cost estimate.

Is there any litigation against Nine Reflex?

No litigation is declared on Nine Reflex's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Dadar Naigaon