New Manibhuvan
A mixed project by Amul Enterprises in Andheri, Mumbai Suburban.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Amul Enterprises · Partnership
- Project type
- Mixed
- Land area
- 1,069 m² · Permissible built-up (FSI) 3,348 m²
- Total units
- 32 across 2 wings
- Estimated cost
- ₹43.2 Cr
- Parking
- 25 four-wheeler · 0 two-wheeler
- Held outside open sale
- 18 rehab
- Application date
- 19 Jan 2026
WING A & WING B
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| WING A | 7 of 10 proposed | 12 |
| WING B | 7 of 10 proposed | 20 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- · CA/86/9600
- Structural engineer
- SURA & ASSOCIATES · STR/840002656
- Project bank
- THE SHAMRAO VITHAL COOPERATIVE BANK
Where it sits
Andheri, Mumbai Suburban — 400057.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
New Manibhuvan: common questions
Is New Manibhuvan RERA registered?
Yes. New Manibhuvan is registered with MahaRERA under registration number PM1180002502660, granted on 9 March 2026. As of July 2026, the registration is active.
What is the possession date of New Manibhuvan?
The developer has declared completion by December 2026 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of New Manibhuvan?
New Manibhuvan is developed by Amul Enterprises, the promoter named in its MahaRERA registration.
Where is New Manibhuvan located?
New Manibhuvan is in Andheri, Mumbai (PIN 400057), Maharashtra, as declared in its RERA registration.
How many units does New Manibhuvan have, and how many are sold?
New Manibhuvan has 32 units on its RERA registration. 0 were reported sold as of July 2026, leaving 32 unsold.
How much construction of New Manibhuvan is complete?
By the developer's own quarterly filing, 94% of the work is done, measured against the project's cost estimate.
Is there any litigation against New Manibhuvan?
No litigation is declared on New Manibhuvan's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Andheri
- 153 East · Mumbai Suburban
- Advent Joy Pragati · Mumbai Suburban
- Bhoomi Amogh · Mumbai Suburban
- Mesacon Harmony · Mumbai Suburban
- Mesacon Magic Carpet · Mumbai Suburban
- Pearl Heaven I · Mumbai Suburban
- Athena · Mumbai Suburban
- Milan Aura · Mumbai Suburban