In ExtensionP51800055265Registered Mar 2024Delayed 365dExtension2 red flags

Misty Heights

A others project by Misty Land Developers Private Limited in Deonar, Mumbai Suburban.

Data as of Oct 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Oct 2026.

Construction
9%
cost-weighted
Declared completion
Dec 2027
delayed 365d
Units sold
0 / 116
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Misty Land Developers Private Limited · Company
Project type
Others
Land area
1,706 m² · Permissible built-up (FSI) 5,528 m²
Total units
116 across 1 wing
Estimated cost
₹36.1 Cr
Land ownership
Promoter is the landowner
Held outside open sale
43 rehab
Application date
04 Feb 2024
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA1 of 1 proposed116
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
BH Wadhwa and Chhadva Associates · CA/82/7288
Structural engineer
Project bank
UNION BANK OF INDIA
Location

Where it sits

Deonar, Mumbai Suburban — 400088.

Locality
Deonar
District
Mumbai Suburban
Authority
P-16547/2023/(96/A/2 )/M/E Ward/DEONAR-E/CC/1/New
Red flags

2 flags on this project

What they are and why they matter — in the full report.

Unlock the 2 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Misty Heights: common questions

Is Misty Heights RERA registered?

Yes. Misty Heights is registered with MahaRERA under registration number P51800055265, granted on 14 March 2024. As of October 2026, the registration is active under a MahaRERA extension.

What is the possession date of Misty Heights?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original December 2026. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Misty Heights?

Misty Heights is developed by Misty Land Developers Private Limited, the promoter named in its MahaRERA registration.

Where is Misty Heights located?

Misty Heights is in Deonar, Mumbai (PIN 400088), Maharashtra, as declared in its RERA registration.

How many units does Misty Heights have, and how many are sold?

Misty Heights has 116 units on its RERA registration. 2 were reported sold as of October 2026, leaving 114 unsold.

How much construction of Misty Heights is complete?

By the developer's own quarterly filing, 9% of the work is done, measured against the project's cost estimate.

Is there any litigation against Misty Heights?

No litigation is declared on Misty Heights's MahaRERA record as of October 2026. A clean record reflects what was filed, not a legal title check.