In ExtensionP52100052702Registered Sept 2023Delayed 1127dExtension1 red flag

Lotus Treya

A others project by Lotus Landmarks in Kothrud, Pune.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
14%
cost-weighted
Declared completion
Jan 2030
delayed 1127d
Units sold
0 / 96
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Lotus Landmarks · Partnership
Project type
Others
Land area
3,448 m² · Permissible built-up (FSI) 8,696 m²
Total units
96 across 1 wing
Estimated cost
₹35.8 Cr
Land ownership
Promoter is the landowner
Parking
58 four-wheeler · 141 two-wheeler
Held outside open sale
42 rehab
Application date
29 Aug 2023
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA14 of 14 proposed96
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
ARCH AMANNULLA INAMDAR
Structural engineer
MR SATISH WAMAN GIRI
Project bank
AXIS BANK
Location

Where it sits

Kothrud, Pune — 411038.

Locality
Kothrud
District
Pune
Authority
Pune Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99

Lotus Treya: common questions

Is Lotus Treya RERA registered?

Yes. Lotus Treya is registered with MahaRERA under registration number P52100052702, granted on 22 September 2023. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Lotus Treya?

The developer has declared completion by January 2030 in its MahaRERA filing, revised from the original December 2026. The record shows the project running 1127 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Lotus Treya?

Lotus Treya is developed by Lotus Landmarks, the promoter named in its MahaRERA registration.

Where is Lotus Treya located?

Lotus Treya is in Kothrud, Pune (PIN 411038), Maharashtra, as declared in its RERA registration.

How many units does Lotus Treya have, and how many are sold?

Lotus Treya has 96 units on its RERA registration. 0 were reported sold as of September 2026, leaving 96 unsold.

How much construction of Lotus Treya is complete?

By the developer's own quarterly filing, 14% of the work is done, measured against the project's cost estimate.

Is there any litigation against Lotus Treya?

No litigation is declared on Lotus Treya's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.