RERA projects in Wadgaon, Pune
20 projects are registered with MahaRERA in Wadgaon, Pune: 7 ongoing, 7 completed, and 6 lapsed, deregistered or in abeyance. 8 are running behind the completion date declared to RERA.
Most active builders here: Kiran Buildcon (1), Naiknavare Township LLP. (1), Singh Buildcon & Solutions (1), Lok8 Infra Private Limited (1), Unnamed Promoter 115662 (1).
- Skyview ParkP52100076965Kiran Buildcon · In extension · completion Mar 2027 · delayed 365d
- AranyaP52100052216Naiknavare Township LLP. · Active · completion Mar 2027
- Singh TowerP50900079886Singh Buildcon & Solutions · Active · completion Dec 2030
- Lok8 GrandeurP51000077074Lok8 Infra Private Limited · Active · completion Dec 2027
- RudrakshaP52100055171Unnamed Promoter 115662 · Active · completion Dec 2027
- Avasa Meadows TalegaonP52100047658Naiknavare Township LLP · Lapsed · completion Dec 2025
- Iristo GoldP52100046568M/s Iristo Developers LLP · Lapsed · completion Jan 2026 · delayed 365d
- Krishna Amrut PalaceP50900034953Krishnakanchan Developers · Lapsed · completion Dec 2024
- Orion PlusP52000026308Unnamed Promoter 79466 · Completed · completion Sept 2023
- Star PrimeP50900025378Unnamed Promoter 81084 · Deregistered · completion Sept 2022
- ThakrewadiP50900019910Vyankatesh Infraalliance · In extension · completion Jan 2030 · delayed 1812d
- Aditya Vardhan HeightsP52100015460Shree Ganesh Developers · In extension · completion Dec 2026 · delayed 2557d
- Kalpana ResidencyP52100015322Om Shree Associates · Lapsed · completion Dec 2022
- Akshay AanganP52100014607Akshay Properties · Completed · completion Mar 2019
- Riddhi ApartmentP50900014490Unnamed Promoter 113780 · Completed · completion Mar 2019
- Mount VistaP52100014425Tirupati Lands and Building Constructions LLP · Lapsed · completion Oct 2025 · delayed 183d
- AlankapuriP52100010797Laigude Developers · Completed · completion Aug 2023
- Vidarbhapremier Nagri YavatmalP51000011689Unnamed Promoter 79811 · Completed · completion Dec 2021 · delayed 730d
- Devi CrestP52100003935Devi Construction Co. · Completed · completion Dec 2019 · delayed 365d
- Green Glory B WingP52100002374Shree Mahalaxmi Group · Completed · completion Sept 2021 · delayed 914d