35 projects are registered with MahaRERA in Kurla West, Mumbai: 14 ongoing, 13 completed, and 8 lapsed, deregistered or in abeyance. 8 are running behind the completion date declared to RERA.
Most active builders here: Dadamiya Infrastructure LLP (2), Nisar Properties Pvt. Ltd. (2), Associated Builders (2), Star Embassy (2), Hari Om Construction (2).
- Dadamiya’s Man'souza HeightPR1180002601930Dadamiya Infrastructure LLP · Active · completion Mar 2028
- Presidence OnePM1180002600761N Khan Construction Works LLP · Active · completion Jan 2030
- Rajal Happy HomeP51800079439Nisar Properties Pvt. Ltd. · Active · completion Dec 2027
- Rehmaniya ApartmentsP51800078660S & S Enterprises · Active · completion Dec 2026
- Urban OrionP51800078516Associated Builders · Active · completion Dec 2027
- Qadri ManzilP51800076978Qadri Constructions · Active · completion Dec 2029
- Dadamiyas EmeraldP51800056273Dadamiya Infrastructure LLP · Active · completion Mar 2027
- Yojan OneP51800028864Meru Realty LLP · Active · completion Sept 2026
- Twin GalaxyP51800015405Twin Developers · In extension · completion Dec 2027 · delayed 1827d
- Livsmart KurlaP51800000340D. K. Realty (India) Pvt. Ltd. · In extension · completion Mar 2028 · delayed 2264d
- Asma EnclavePR1180002600996Faith K S Infra LLP · Active · completion Dec 2029
- Amber ApartmentPR1180002600756Aman Developers · Lapsed · completion Feb 2026
- Elite SquarePM1180002502594I&a Realty Private Limited · Active · completion Jun 2029
- Sayba ArcadiaP51800055257Star Empire · Completed · completion Jul 2026 · delayed 122d
- Manshaya ApartmentsP51800053650Mass Construction · Deregistered · completion Dec 2026
- Sayba SapphireP51800052773Star Embassy · Completed · completion Dec 2026
- Emarald CastleP51800052182Shreeji Buildcon Projects Private Limited · Active · completion Dec 2027
- Elite ResidencyP51800048557Elite Construction Co. · In extension · completion Jun 2027 · delayed 546d
- Darpan Niketan Cooperative SocietyP51800048133Bricks and Blocks Construction LLP · Completed · completion May 2025
- ViewstoneP51800047980Kherectors LLP · Completed · completion Dec 2025
- Retiwala HeightsP51800046591Unnamed Promoter 125596 · Lapsed · completion Dec 2025 · delayed 364d
- Dadamiyas Deluxe ApartmentP51800030492Dadamiya Infrastructure & Deluxe Infra · Completed · completion Mar 2023
- Platinum HeightsP51800029842N I Enterprises · Completed · completion Dec 2024
- Sayba IconP51800027784Star Embassy · Completed · completion Jun 2024
- Jaswanti BlissP51800027448Ashray Estates · Completed · completion Sept 2024
- S.K.Milan ResidencyP51800022943S.k.construction · Lapsed · completion Mar 2024 · delayed 365d
- Pearl Hans Residency - G WingP51800022670Hari Om Construction · Completed · completion Dec 2025
- Pearl Hans Residency - H WingP51800022506Hari Om Construction · Completed · completion Dec 2025
- CornerstoneP51800017746Ojas Corporation · Completed · completion Dec 2022
- Arman SRA CHS Ltd Building no 2P51800016642Associated Builders · Lapsed · completion Dec 2022
- Premier Exotica IIP51800016598Housing Development and Infrastructure Ltd · Lapsed · completion Dec 2019 · delayed 365d
- Nandadeep ResidencyP51800015173Vinayaka Realtors and Developers · Lapsed · completion Nov 2023 · delayed 364d
- Premier Exotica IP51800004431Housing Development and Infrastructure Ltd · Lapsed · completion Jan 2021
- Agastya Corporate park -Wing BP51900002300PRL Agastya Private Limited · Completed · completion Dec 2017
- Rajal - Om Jaishriram CHS LtdP51800002124Nisar Properties Pvt. Ltd. · Completed · completion Dec 2017