ActiveP52100055730Registered Apr 2024No active red flags

Keystone Bliss 2

A plotted project by Rucha Associates in DHAYARI, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
83%
cost-weighted
Declared completion
Dec 2027
no delay on record
Units sold
9 / 31
29% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Rucha Associates · Partnership
Project type
Plotted
Land area
10,048 m²
Total units
31
Estimated cost
₹6.3 Cr
Land ownership
Promoter is the landowner
Application date
29 Mar 2024
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/2003/31278
Structural engineer
Project bank
STATE BANK OF INDIA
Location

Where it sits

DHAYARI, Pune — 411041.

Locality
DHAYARI
District
Pune
Authority
PUNE MUNICIPAL CORPORATION
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Keystone Bliss 2: common questions

Is Keystone Bliss 2 RERA registered?

Yes. Keystone Bliss 2 is registered with MahaRERA under registration number P52100055730, granted on 16 April 2024. As of July 2026, the registration is active.

What is the possession date of Keystone Bliss 2?

The developer has declared completion by December 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Keystone Bliss 2?

Keystone Bliss 2 is developed by Rucha Associates, the promoter named in its MahaRERA registration.

Where is Keystone Bliss 2 located?

Keystone Bliss 2 is in Dhayari, Pune (PIN 411041), Maharashtra, as declared in its RERA registration.

How many units does Keystone Bliss 2 have, and how many are sold?

Keystone Bliss 2 has 31 units on its RERA registration. 9 were reported sold as of July 2026, leaving 22 unsold.

How much construction of Keystone Bliss 2 is complete?

By the developer's own quarterly filing, 83% of the work is done, measured against the project's cost estimate.

Is there any litigation against Keystone Bliss 2?

No litigation is declared on Keystone Bliss 2's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.