In ExtensionP52100025778Registered Jul 2020Delayed 549dExtensionNo active red flags

Kalpataru

A residential / group housing project by NKG Constructions LLP in Aalandi Markal Road, Charholi Khurd, Aalandi, Pune.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
77%
cost-weighted
Declared completion
Dec 2026
delayed 549d
Units sold
42 / 84
50% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
NKG Constructions LLP · Partnership
Project type
Residential / Group Housing
Land area
3,350 m² · Permissible built-up (FSI) 3,258 m²
Total units
84 across 2 wings
Estimated cost
₹10.4 Cr
Land ownership
Promoter is the landowner
Held outside open sale
18 landowner/investor share
Application date
10 Jul 2020
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA8 of 8 proposed42
NA8 of 8 proposed42
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Drushtikcon Architects & Corelates · CA/2002/29007
Structural engineer
Pravin Bansode
Project bank
BANK OF MAHARASHTRA
Location

Where it sits

Aalandi Markal Road, Charholi Khurd, Aalandi, Pune — 412105.

Locality
Aalandi Markal Road, Charholi Khurd, Aalandi
District
Pune
Authority
Pune Municipal Corporation
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Kalpataru: common questions

Is Kalpataru RERA registered?

Yes. Kalpataru is registered with MahaRERA under registration number P52100025778, granted on 14 July 2020. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Kalpataru?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original June 2025. The record shows the project running 549 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Kalpataru?

Kalpataru is developed by NKG Constructions LLP, the promoter named in its MahaRERA registration.

Where is Kalpataru located?

Kalpataru is in Aalandi, Pune (PIN 412105), Maharashtra, as declared in its RERA registration.

How many units does Kalpataru have, and how many are sold?

Kalpataru has 84 units on its RERA registration. 42 were reported sold as of September 2026, leaving 42 unsold.

How much construction of Kalpataru is complete?

By the developer's own quarterly filing, 77% of the work is done, measured against the project's cost estimate.

Is there any litigation against Kalpataru?

No litigation is declared on Kalpataru's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.