Status & progress

Per MahaRERA record as of Jul 2026.

Construction
18%
cost-weighted
Declared completion
Dec 2028
no delay on record
Units sold
12 / 77
16% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Shree Maruti Buildcon · Partnership
Project type
Commercial
Land area
1,555 m² · Permissible built-up (FSI) 7,075 m²
Total units
77 across 1 wing
Estimated cost
₹36.4 Cr
Parking
76 four-wheeler · 139 two-wheeler
Application date
12 Sept 2024
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA16 of 16 proposed77
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/92/14812
Structural engineer
· -
Project bank
ICICI BANK LIMITED
Location

Where it sits

RAHATANI, Pune — 411057.

Locality
RAHATANI
District
Pune
Authority
Pimpri Chinchwad Municipal Corporation
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Kalp One: common questions

Is Kalp One RERA registered?

Yes. Kalp One is registered with MahaRERA under registration number PC1260002400075, granted on 8 October 2024. As of July 2026, the registration is active.

What is the possession date of Kalp One?

The developer has declared completion by December 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Kalp One?

Kalp One is developed by Shree Maruti Buildcon, the promoter named in its MahaRERA registration.

Where is Kalp One located?

Kalp One is in Rahatani, Pune (PIN 411057), Maharashtra, as declared in its RERA registration.

How many units does Kalp One have, and how many are sold?

Kalp One has 77 units on its RERA registration. 18 were reported sold as of July 2026, leaving 59 unsold.

How much construction of Kalp One is complete?

By the developer's own quarterly filing, 18% of the work is done, measured against the project's cost estimate.

Is there any litigation against Kalp One?

No litigation is declared on Kalp One's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.