ActiveP51800079037Registered Jan 2025No active red flags

JVLR 60

A others project by Rajhem Builders and Developers LLP in ANDHERI, Mumbai Suburban.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
29%
cost-weighted
Declared completion
Dec 2028
no delay on record
Units sold
31 / 172
18% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Rajhem Builders and Developers LLP · Partnership
Project type
Others
Land area
923 m² · Permissible built-up (FSI) 5,526 m²
Total units
172 across 1 wing
Estimated cost
₹38.6 Cr
Held outside open sale
13 landowner/investor share · 62 reserved
Application date
16 Oct 2024
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA19 of 19 proposed172
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
CREATIVE CONSULTANCY · V/152/LS
Structural engineer
Rupesh Chowhary
Project bank
ICICI BANK LIMITED
Location

Where it sits

ANDHERI, Mumbai Suburban — 400060.

Locality
ANDHERI
District
Mumbai Suburban
Authority
SLUM REHABILITATION AUTHORITY
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

JVLR 60: common questions

Is JVLR 60 RERA registered?

Yes. JVLR 60 is registered with MahaRERA under registration number P51800079037, granted on 31 January 2025. As of July 2026, the registration is active.

What is the possession date of JVLR 60?

The developer has declared completion by December 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of JVLR 60?

JVLR 60 is developed by Rajhem Builders and Developers LLP, the promoter named in its MahaRERA registration.

Where is JVLR 60 located?

JVLR 60 is in Andheri, Mumbai (PIN 400060), Maharashtra, as declared in its RERA registration.

How many units does JVLR 60 have, and how many are sold?

JVLR 60 has 172 units on its RERA registration. 38 were reported sold as of July 2026, leaving 134 unsold.

How much construction of JVLR 60 is complete?

By the developer's own quarterly filing, 29% of the work is done, measured against the project's cost estimate.

Is there any litigation against JVLR 60?

No litigation is declared on JVLR 60's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.