J D Palms
A mixed project by J D Housing LLP in Near J D PARK SOCIETY, Thane.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- J D Housing LLP · Limited Liability Partnership
- Project type
- Mixed
- Land area
- 1,584 m² · Permissible built-up (FSI) 4,708 m²
- Total units
- 87 across 1 wing
- Estimated cost
- ₹9.3 Cr
- Land ownership
- Promoter is the landowner
- Parking
- 24 four-wheeler · 55 two-wheeler
- Application date
- 21 Nov 2025
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 8 of 8 proposed | 87 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- · CA/2001/28448
- Structural engineer
- · STATE/R/2024/APL/13098
- Project bank
- HDFC BANK
Where it sits
Near J D PARK SOCIETY, Thane — 421601.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
J D Palms: common questions
Is J D Palms RERA registered?
Yes. J D Palms is registered with MahaRERA under registration number PM1330002502557, granted on 2 March 2026. As of July 2026, the registration is active.
What is the possession date of J D Palms?
The developer has declared completion by March 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of J D Palms?
J D Palms is developed by J D Housing LLP, the promoter named in its MahaRERA registration.
Where is J D Palms located?
J D Palms is in Thane (PIN 421601), Maharashtra, as declared in its RERA registration.
How many units does J D Palms have, and how many are sold?
J D Palms has 87 units on its RERA registration. 0 were reported sold as of July 2026, leaving 87 unsold.
How much construction of J D Palms is complete?
By the developer's own quarterly filing, 50% of the work is done, measured against the project's cost estimate.
Is there any litigation against J D Palms?
No litigation is declared on J D Palms's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
RERA projects nearby
- Shantaram Park Residency · Thane
- Aghav Resideny · Thane
- Mirador Utsav Phase 1 · Thane
- Fennel G · Thane
- Tulip N1 N2 N3 O1 · Thane
- Building No 5 Vardhaman Vatika Pahse II · Thane
- Chintamani Meadows · Thane
- La Luxuria · Thane