In ExtensionP51800004521Registered Aug 2017Delayed 3563dExtension1 red flag

Integrated Arya

A others project by Integrated Spaces Limited in Narayan Nagar, Ghatkopar West, Mumbai Suburban.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
103%
cost-weighted
Declared completion
Dec 2028
delayed 3563d
Units sold
82 / 167
49% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Integrated Spaces Limited · Company
Project type
Others
Land area
3,252 m² · Permissible built-up (FSI) 7,864 m²
Total units
167 across 1 wing
Estimated cost
₹33.7 Cr
Held outside open sale
65 rehab
Application date
29 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA11 of 11 proposed167
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
YMS CONSULTANTS LIMITED · R-151/LS
Structural engineer
Project bank
IDBI BANK
Location

Where it sits

Narayan Nagar, Ghatkopar West, Mumbai Suburban — 400086.

Locality
Narayan Nagar, Ghatkopar West
District
Mumbai Suburban
Authority
MUNICIPAL CORPORATION OF GREATER MUMBAI
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Integrated Arya: common questions

Is Integrated Arya RERA registered?

Yes. Integrated Arya is registered with MahaRERA under registration number P51800004521, granted on 9 August 2017. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Integrated Arya?

The developer has declared completion by December 2028 in its MahaRERA filing, revised from the original March 2019. The record shows the project running 3563 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Integrated Arya?

Integrated Arya is developed by Integrated Spaces Limited, the promoter named in its MahaRERA registration.

Where is Integrated Arya located?

Integrated Arya is in Ghatkopar West, Mumbai (PIN 400086), Maharashtra, as declared in its RERA registration.

How many units does Integrated Arya have, and how many are sold?

Integrated Arya has 167 units on its RERA registration. 82 were reported sold as of July 2026, leaving 85 unsold.

How much construction of Integrated Arya is complete?

By the developer's own quarterly filing, 103% of the work is done, measured against the project's cost estimate.

Is there any litigation against Integrated Arya?

2 litigation cases are declared on Integrated Arya's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Ghatkopar West

All RERA projects in Ghatkopar West →

Other projects by Integrated Spaces Limited

All projects by Integrated Spaces Limited →