Status & progress

Per MahaRERA record as of Sept 2026.

Construction
70%
cost-weighted
Declared completion
Sept 2026
delayed 365d
Units sold
22 / 61
36% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
R K Constructions · Partnership
Project type
Residential / Group Housing
Land area
459 m² · Permissible built-up (FSI) 1,365 m²
Total units
61 across 1 wing
Estimated cost
₹18.8 Cr
Parking
24 four-wheeler · 0 two-wheeler
Held outside open sale
30 rehab
Application date
18 Apr 2021
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA22 of 22 proposed61
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
PDA Architects · NA
Structural engineer
Ellora Consultancy Services
Project bank
HDFC BANK
Location

Where it sits

Suparibaug Estate Parel, Mumbai City — 400012.

Locality
Suparibaug Estate Parel
District
Mumbai City
Authority
Municipal Corporation of Greater Mumbai
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Inspire: common questions

Is Inspire RERA registered?

Yes. Inspire is registered with MahaRERA under registration number P51900029171, granted on 3 May 2021. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Inspire?

The developer has declared completion by September 2026 in its MahaRERA filing, revised from the original September 2025. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Inspire?

Inspire is developed by R K Constructions, the promoter named in its MahaRERA registration.

Where is Inspire located?

Inspire is in Suparibaug Estate Parel, Mumbai (PIN 400012), Maharashtra, as declared in its RERA registration.

How many units does Inspire have, and how many are sold?

Inspire has 61 units on its RERA registration. 24 were reported sold as of September 2026, leaving 37 unsold.

How much construction of Inspire is complete?

By the developer's own quarterly filing, 70% of the work is done, measured against the project's cost estimate.

Is there any litigation against Inspire?

No litigation is declared on Inspire's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.