In ExtensionP51800056381Registered May 2024Delayed 365dExtension1 red flag

Horizon Tower

A residential / group housing project by I.R.Developers LLP in Sher -E-Punjab CHS , Andheri East, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
59%
cost-weighted
Declared completion
Mar 2027
delayed 365d
Units sold
0 / 25
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
I.R.Developers LLP · Partnership
Project type
Residential / Group Housing
Land area
836 m² · Permissible built-up (FSI) 2,256 m²
Total units
25 across 1 wing
Estimated cost
₹11.5 Cr
Land ownership
Promoter is the landowner
Parking
35 four-wheeler · 0 two-wheeler
Held outside open sale
12 rehab
Application date
30 Apr 2024
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA16 of 16 proposed25
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Arun Kumar Dube · CA/85/9344
Structural engineer
SK Consultants & Engineers · STATE/R/2024/APL/14234
Project bank
HDFC BANK
Location

Where it sits

Sher -E-Punjab CHS , Andheri East, Mumbai Suburban — 400093.

Locality
Sher -E-Punjab CHS , Andheri East
District
Mumbai Suburban
Authority
P-15959/2023/(368/301 And Other)/K/E Ward/MOGRA/CC/1/New
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Horizon Tower: common questions

Is Horizon Tower RERA registered?

Yes. Horizon Tower is registered with MahaRERA under registration number P51800056381, granted on 31 May 2024. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Horizon Tower?

The developer has declared completion by March 2027 in its MahaRERA filing, revised from the original March 2026. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Horizon Tower?

Horizon Tower is developed by I.r.developers LLP, the promoter named in its MahaRERA registration.

Where is Horizon Tower located?

Horizon Tower is in Andheri East, Mumbai (PIN 400093), Maharashtra, as declared in its RERA registration.

How many units does Horizon Tower have, and how many are sold?

Horizon Tower has 25 units on its RERA registration. 2 were reported sold as of September 2026, leaving 23 unsold.

How much construction of Horizon Tower is complete?

By the developer's own quarterly filing, 59% of the work is done, measured against the project's cost estimate.

Is there any litigation against Horizon Tower?

No litigation is declared on Horizon Tower's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.