H R Heights
A residential / group housing project by Jay Ashapura Developers in AYRE GAON AYRE, Thane.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Jay Ashapura Developers · Partnership
- Project type
- Residential / Group Housing
- Land area
- 358 m² · Permissible built-up (FSI) 1,197 m²
- Total units
- 26 across 1 wing
- Estimated cost
- ₹4.7 Cr
- Land ownership
- Promoter is the landowner
- Held outside open sale
- 9 landowner/investor share
- Application date
- 11 May 2024
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 8 of 8 proposed | 26 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- SHREYAS BRID · (COA no. CA120191107490),
- Structural engineer
- Aditya Deshmukh · STATE/FU2O23/AP UO5005
- Project bank
- BANK OF BARODA
Where it sits
AYRE GAON AYRE, Thane — 421201.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
H R Heights: common questions
Is H R Heights RERA registered?
Yes. H R Heights is registered with MahaRERA under registration number P51700076610, granted on 18 June 2024. As of July 2026, the registration is active.
What is the possession date of H R Heights?
The developer has declared completion by April 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of H R Heights?
H R Heights is developed by Jay Ashapura Developers, the promoter named in its MahaRERA registration.
Where is H R Heights located?
H R Heights is in Ayre Gaon Ayre, Thane (PIN 421201), Maharashtra, as declared in its RERA registration.
How many units does H R Heights have, and how many are sold?
H R Heights has 26 units on its RERA registration. 2 were reported sold as of July 2026, leaving 24 unsold.
How much construction of H R Heights is complete?
By the developer's own quarterly filing, 65% of the work is done, measured against the project's cost estimate.
Is there any litigation against H R Heights?
No litigation is declared on H R Heights's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
RERA projects nearby
- Mahalaxmi Ashish D Wing · Thane
- Mahalaxmi Heights Phase 2 · Thane
- Marathon Nextown Ruby · Thane
- Mangeshi Dazzle II · Thane
- Shree Empire · Thane
- Balaji Annex · Thane
- Arya Ariana · Thane
- Balaji Krishna · Thane