In ExtensionP51800004371Registered Aug 2017Delayed 1918dExtension1 red flag

Gulraj Paradise

A others project by M/s Reliable Construction in MATUNGA, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
61%
cost-weighted
Declared completion
Sept 2026
delayed 1918d
Units sold
23 / 35
66% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
M/s Reliable Construction · Partnership
Project type
Others
Land area
5,693 m² · Permissible built-up (FSI) 22,367 m²
Total units
35 across 2 wings
Estimated cost
₹104.3 Cr
Held outside open sale
8 reserved
Application date
30 Jul 2017
Buildings & units

2 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA25 of 25 proposed16
NA17 of 17 proposed19
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
ATHARVA CONSULTANTS · CA/95/18760
Structural engineer
Hanware Consultants
Project bank
BANK OF BARODA
Location

Where it sits

MATUNGA, Mumbai Suburban — 400019.

Locality
MATUNGA
District
Mumbai Suburban
Authority
SLUM REHABILATION AUTHORITY
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Gulraj Paradise: common questions

Is Gulraj Paradise RERA registered?

Yes. Gulraj Paradise is registered with MahaRERA under registration number P51800004371, granted on 9 August 2017. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Gulraj Paradise?

The developer has declared completion by September 2026 in its MahaRERA filing, revised from the original June 2021. The record shows the project running 1918 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Gulraj Paradise?

Gulraj Paradise is developed by M/s Reliable Construction, the promoter named in its MahaRERA registration.

Where is Gulraj Paradise located?

Gulraj Paradise is in Matunga, Mumbai (PIN 400019), Maharashtra, as declared in its RERA registration.

How many units does Gulraj Paradise have, and how many are sold?

Gulraj Paradise has 35 units on its RERA registration. 24 were reported sold as of September 2026, leaving 11 unsold.

How much construction of Gulraj Paradise is complete?

By the developer's own quarterly filing, 61% of the work is done, measured against the project's cost estimate.

Is there any litigation against Gulraj Paradise?

No litigation is declared on Gulraj Paradise's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.