In ExtensionP51800010794Registered Aug 2017Delayed 366dExtension2 red flags

Green Acres

A residential / group housing project by Nirman Realtors and Developers Ltd in Malad (E), Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
95%
cost-weighted
Declared completion
Dec 2026
delayed 366d
Units sold
0 / 180
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Nirman Realtors and Developers Ltd · Company
Project type
Residential / Group Housing
Land area
4,220 m² · Permissible built-up (FSI) 12,501 m²
Total units
180 across 1 wing
Estimated cost
₹65.6 Cr
Land ownership
Promoter is the landowner
Application date
31 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA23 of 23 proposed180
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
S.S. Associates · CA/2003/31138
Structural engineer
SK Consultants & Engineers · STATE/R/2024/APL/14306
Project bank
NKGSB COOPERATIVE BANK LIMITED
Location

Where it sits

Malad (E), Mumbai Suburban — 400097.

Locality
Malad (E)
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority
Red flags

2 flags on this project

What they are and why they matter — in the full report.

Unlock the 2 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Green Acres: common questions

Is Green Acres RERA registered?

Yes. Green Acres is registered with MahaRERA under registration number P51800010794, granted on 31 August 2017. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Green Acres?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original December 2025. The record shows the project running 366 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Green Acres?

Green Acres is developed by Nirman Realtors and Developers Ltd, the promoter named in its MahaRERA registration.

Where is Green Acres located?

Green Acres is in Malad East, Mumbai (PIN 400097), Maharashtra, as declared in its RERA registration.

How many units does Green Acres have, and how many are sold?

Green Acres has 180 units on its RERA registration. 112 were reported sold as of September 2026, leaving 68 unsold.

How much construction of Green Acres is complete?

By the developer's own quarterly filing, 95% of the work is done, measured against the project's cost estimate.

Is there any litigation against Green Acres?

11 litigation cases are declared on Green Acres's MahaRERA record. The full report lists each case with its court and status.