In ExtensionP52100046952Registered Sept 2022Delayed 730dExtension2 red flags

Golden Court

A commercial project by Silverleaf landmarks llp in UNDRI, Pune.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
98%
cost-weighted
Declared completion
Jun 2027
delayed 730d
Units sold
0 / 65
0% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Silverleaf landmarks llp · Others
Project type
Commercial
Land area
3,101 m² · Permissible built-up (FSI) 10,714 m²
Total units
65 across 1 wing
Estimated cost
₹26 Cr
Land ownership
Promoter is the landowner
Application date
14 Jul 2022
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA7 of 7 proposed65
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Group Consultants · CA/2002/28913
Structural engineer
S K Consultants & Engineers · STATE/R/2024/APL/14234
Project bank
HDFC BANK
Location

Where it sits

UNDRI, Pune — 411060.

Locality
UNDRI
District
Pune
Authority
Pune Municipal Corporation
Red flags

2 flags on this project

What they are and why they matter — in the full report.

Unlock the 2 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Golden Court: common questions

Is Golden Court RERA registered?

Yes. Golden Court is registered with MahaRERA under registration number P52100046952, granted on 26 September 2022. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Golden Court?

The developer has declared completion by June 2027 in its MahaRERA filing, revised from the original June 2025. The record shows the project running 730 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Golden Court?

Golden Court is developed by Silverleaf Landmarks LLP, the promoter named in its MahaRERA registration.

Where is Golden Court located?

Golden Court is in Undri, Pune (PIN 411060), Maharashtra, as declared in its RERA registration.

How many units does Golden Court have, and how many are sold?

Golden Court has 65 units on its RERA registration. 54 were reported sold as of September 2026, leaving 11 unsold.

How much construction of Golden Court is complete?

By the developer's own quarterly filing, 98% of the work is done, measured against the project's cost estimate.

Is there any litigation against Golden Court?

2 litigation cases are declared on Golden Court's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Undri

All RERA projects in Undri →