In ExtensionP52100026022Registered Aug 2020Delayed 549dExtension1 red flag

Emerald Bay Building 3

A residential / group housing project by Pune Projects LLP in NA, Pune.

Data as of May 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of May 2026.

Construction
47%
mean of activity checklist
Declared completion
Dec 2026
delayed 549d
Units sold
82 / 84
98% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Pune Projects LLP · Partnership
Project type
Residential / Group Housing
Land area
735 m² · Permissible built-up (FSI) 9,605 m²
Total units
84 across 1 wing
Land ownership
Promoter is the landowner
Application date
05 Aug 2020
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA25 of 25 proposed84
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Abhijit Konde
Structural engineer
JW Consultants LLP
Project bank
INDUSIND BANK
Location

Where it sits

NA, Pune — 411036.

Locality
NA
District
Pune
Authority
Pune Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Emerald Bay Building 3: common questions

Is Emerald Bay Building 3 RERA registered?

Yes. Emerald Bay Building 3 is registered with MahaRERA under registration number P52100026022, granted on 9 August 2020. As of May 2026, the registration is active under a MahaRERA extension.

What is the possession date of Emerald Bay Building 3?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original June 2025. The record shows the project running 549 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Emerald Bay Building 3?

Emerald Bay Building 3 is developed by Pune Projects LLP, the promoter named in its MahaRERA registration.

Where is Emerald Bay Building 3 located?

Emerald Bay Building 3 is in Pune (PIN 411036), Maharashtra, as declared in its RERA registration.

How many units does Emerald Bay Building 3 have, and how many are sold?

Emerald Bay Building 3 has 84 units on its RERA registration. 82 were reported sold as of May 2026, leaving 2 unsold.

Is there any litigation against Emerald Bay Building 3?

5 litigation cases are declared on Emerald Bay Building 3's MahaRERA record. The full report lists each case with its court and status.