Dream Aspire
A residential / group housing project by Dream India Builders in Anand Nagar, Mumbai Suburban.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Dream India Builders · Partnership
- Project type
- Residential / Group Housing
- Land area
- 2,345 m² · Permissible built-up (FSI) 5,465 m²
- Total units
- 129 across 1 wing
- Estimated cost
- ₹95 Cr
- Land ownership
- Promoter is the landowner
- Parking
- 114 four-wheeler · 0 two-wheeler
- Application date
- 06 Nov 2023
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 23 of 23 proposed | 129 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- · CA/2018/99003
- Structural engineer
- STRUBUILD CONSULTANT LLP · STR/Q/04
- Project bank
- AXIS BANK
Where it sits
Anand Nagar, Mumbai Suburban — 400102.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Dream Aspire: common questions
Is Dream Aspire RERA registered?
Yes. Dream Aspire is registered with MahaRERA under registration number P51800053836, granted on 1 December 2023. As of July 2026, the registration is active.
What is the possession date of Dream Aspire?
The developer has declared completion by December 2026 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Dream Aspire?
Dream Aspire is developed by Dream India Builders, the promoter named in its MahaRERA registration.
Where is Dream Aspire located?
Dream Aspire is in Anand Nagar, Mumbai (PIN 400102), Maharashtra, as declared in its RERA registration.
How many units does Dream Aspire have, and how many are sold?
Dream Aspire has 129 units on its RERA registration. 114 were reported sold as of July 2026, leaving 15 unsold.
How much construction of Dream Aspire is complete?
By the developer's own quarterly filing, 35% of the work is done, measured against the project's cost estimate.
Is there any litigation against Dream Aspire?
No litigation is declared on Dream Aspire's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Anand Nagar
- Sonai · Pune
- PSK Skylar · Thane
- Verona · Mumbai Suburban
- Sani Mascot · Mumbai Suburban
- A. H. Heights · Mumbai Suburban
- Satellite Heights · Mumbai Suburban
- Lashkaria Pearl · Mumbai Suburban
- Platinum Residency · Mumbai Suburban