In ExtensionP51800080143Registered Apr 2025Delayed 366dExtension1 red flag

Diwali Darshan

A residential / group housing project by Omkar Engineers and Contractors in BORIVALI EAST, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
81%
cost-weighted
Declared completion
Feb 2027
delayed 366d
Units sold
2 / 71
3% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Omkar Engineers and Contractors · Partnership
Project type
Residential / Group Housing
Land area
877 m² · Permissible built-up (FSI) 2,761 m²
Total units
71 across 1 wing
Estimated cost
₹27.6 Cr
Land ownership
Promoter is the landowner
Parking
33 four-wheeler · 0 two-wheeler
Held outside open sale
44 rehab
Application date
08 Oct 2024
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA19 of 19 proposed71
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
ABHIJIT MEHTA
Structural engineer
SURA AND ASSOCIATES
Project bank
BANK OF BARODA
Location

Where it sits

BORIVALI EAST, Mumbai Suburban — 400066.

Locality
BORIVALI EAST
District
Mumbai Suburban
Authority
CHE/WSII/1191/R/C/337(NEW)
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Diwali Darshan: common questions

Is Diwali Darshan RERA registered?

Yes. Diwali Darshan is registered with MahaRERA under registration number P51800080143, granted on 30 April 2025. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Diwali Darshan?

The developer has declared completion by February 2027 in its MahaRERA filing, revised from the original January 2026. The record shows the project running 366 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Diwali Darshan?

Diwali Darshan is developed by Omkar Engineers and Contractors, the promoter named in its MahaRERA registration.

Where is Diwali Darshan located?

Diwali Darshan is in Borivali East, Mumbai (PIN 400066), Maharashtra, as declared in its RERA registration.

How many units does Diwali Darshan have, and how many are sold?

Diwali Darshan has 71 units on its RERA registration. 2 were reported sold as of September 2026, leaving 69 unsold.

How much construction of Diwali Darshan is complete?

By the developer's own quarterly filing, 81% of the work is done, measured against the project's cost estimate.

Is there any litigation against Diwali Darshan?

1 litigation case is declared on Diwali Darshan's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Borivali East