Divyash Capital
A commercial project by Lacom Consultancy LLP in Bavdhan Budruk, Pune.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Lacom Consultancy LLP · Limited Liability Partnership
- Project type
- Commercial
- Land area
- 6,369 m² · Permissible built-up (FSI) 6,070 m²
- Total units
- 23 across 1 wing
- Estimated cost
- ₹83.6 Cr
- Parking
- 185 four-wheeler · 216 two-wheeler
- Application date
- 05 Jun 2025
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 10 of 16 proposed | 23 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- · 848480
- Structural engineer
- Project bank
- ICICI BANK LIMITED
Where it sits
Bavdhan Budruk, Pune — 411021.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Divyash Capital: common questions
Is Divyash Capital RERA registered?
Yes. Divyash Capital is registered with MahaRERA under registration number PC1261012501265, granted on 20 October 2025. As of July 2026, the registration is active.
What is the possession date of Divyash Capital?
The developer has declared completion by December 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Divyash Capital?
Divyash Capital is developed by Lacom Consultancy LLP, the promoter named in its MahaRERA registration.
Where is Divyash Capital located?
Divyash Capital is in Bavdhan Budruk, Pune (PIN 411021), Maharashtra, as declared in its RERA registration.
How many units does Divyash Capital have, and how many are sold?
Divyash Capital has 23 units on its RERA registration. 0 were reported sold as of July 2026, leaving 23 unsold.
How much construction of Divyash Capital is complete?
By the developer's own quarterly filing, 45% of the work is done, measured against the project's cost estimate.
Is there any litigation against Divyash Capital?
No litigation is declared on Divyash Capital's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Bavdhan Budruk
- WYCE Exclucity E F I · Pune
- 7 Anshul · Pune
- Padmavati Hills A Wing · Pune
- Anvi Serenity · Pune
- Kekarav Phase III · Pune
- Gloria Grand · Pune
- Geras Isle Royale Tower 4 and 5 · Pune
- Purva Aspire · Pune