RERA projects in Pune district
12,486 projects are registered with MahaRERA in Pune. Of the 4,911 still under construction, 1,213 have passed the completion date their builder declared to RERA.
3,698
Ongoing, on schedule
1,213
Ongoing, past due date
5,179
Completed
2,396
Lapsed or deregistered
All projects, page 53
Showing 5,201–5,300 of 12,486, newest registrations first.
- SENSORIUM, Phase VIJoyville Shapoorji Housing Private Limited, MaanP52100045257OngoingSept 2026
- Parisar ApartmentFortune Developers, ErrandwaneP52100035108OngoingDec 2026
- Manhattan-E BuildingPride Builders LLP, CharholiP52100045218LapsedDec 2024
- Shree Swami Samarth ApartmentGanesh NagarP52100035089CompletedMay 2025
- MarvelM/s Shelter 24, KiwaleP52100035153LapsedDec 2025
- Mokate HeritageMokate Constructions, KothrudP52100035155CompletedDec 2024
- Tanish Orbit Plot EKalpdeep Associates, Charholi BudrukP52100045276CompletedJun 2023
- Aditya Apartments CondominiumKelkar Housing LLP, KothrudP52100035170CompletedNov 2024
- Majestique Signature Towers C5M/s. Samarth Builders, BalewadiP52100035139CompletedDec 2026
- Stellar RhythmmWakadkar Patil Associates LLP, WakadP52100035161LapsedDec 2024
- The MiracleM/s Vijayraj Associates, PunawaleP52100035142LapsedMar 2024
- Aditi Sadan CHSLKelkar Pinnac Housing LLP, Sanewadi AundhP52100045268CompletedDec 2024
- Wishful 60 ExoticaDeshpande Waikar Landmark LLP, Thaksen NagarP52100035104OngoingApr 2027
- Bramhacorp Townhouse BContigo Infrastructures LLP, BalewadiP52100045228OngoingDec 2026
- RD MadhukoshM/s Rachana Developers, KasarwadiP52100035150CompletedDec 2025
- Sparsh AsterShree Enterprises, KasaramboliP52100035183In extensionDec 202612 months late
- SanketRavetkar Realties, Bhusari ColonyP52100035120CompletedSept 2025
- Zainab Be HeightsK P Construction, Nana PethP52100045217In extensionDec 20262.8 years late
- Lodha Pune NIBM Project-Tower 10Lodha Developers Limited, MohhamdwadiP52100035060OngoingApr 2027
- Shankeshwar PearlS P Developers, RavetP52100035074CompletedDec 2025
- 18 EastMerlin Projects Limited, MundhwaP52100035065In extensionMar 20276 months late
- Vikram ResidencyVikram Landmarks, Vadgaon BudrukP52100035064In extensionMay 20272.0 years late
- Rose Gardenia Phase IIRose Dream Developers, KiwaleP52100035063OngoingSept 2026
- The Silver Altair Tower-CSilver Star Group, RavetP52100035075OngoingMar 2027
- Silver ParadiseM/s Silver Paradise, Pimple GuravP52100035077CompletedMar 2026
- Pinnacle Northern GatesKoregaon ParkP52100035049In extensionDec 20273.0 years late
- Amarillo TownWakadkar Brothers, RavetP52100035039CompletedDec 2025
- 66 Avenue A B C BuildingR R Lunkad Landmarks LLPP52100035034LapsedJun 2025
- RatnankurRanjekar Realty LLP, KothrudP52100035032CompletedOct 2025
- The SagaNest Saswad Realty LLP, Pradhikaran NigdiP52100035028In extensionSept 20262.5 years late
- Thorat HeightsJagdamba Developers, ThoratnagarP52100035047CompletedAug 2026
- Opulent StarlitOpulent Developers, GhorpadiP52100035046In extensionJun 202712 months late
- Radha Anand Co-Operative Housing SocietyKiyaara Buildcon, ErandwaneP52100035043In extensionDec 20272.8 years late
- Tanish Orbit Plot BKalpdeep Developers, Charholi BudrukP52100035041CompletedJun 2023
- ShreepushpaDeepali Civil Project, NarayangaonP52100034889LapsedDec 2024
- Pacific TowerChaitanya DevelopersP52100034823In extensionSept 202718 months late
- Joyville Hadapsar Annexe Phase 15Joyville Shapoorji Housing Private Limited, ShewalewadiP52100034911LapsedJun 2026
- Top Towers - ARaga Developers, WakadP52100034929CompletedJun 2026
- Millennium AtlasMillennium Developers, TathawadeP52100035007CompletedDec 2023
- Vision RhythmNavya Associates, DudulgaonP52100034825LapsedApr 2025
- Venu TowerVighnaharta Developers, BhosariP52100034805LapsedMar 2026
- Shreeyash ApartmentSomwar PethP52100034846LapsedJun 2024
- Pristine Purvrang Part 2Padmavati Homes, Siddheshwar NagarP52100034900LapsedDec 2023
- Bharat LeelaaBharat Leelaa Developers, HaveliP52100035009In extensionDec 20304.5 years late
- Sumukh ResidencySamartha Buildcons, Talegaon DabhadeP52100034831CompletedMar 2024
- Eco Tower Phase 2Vascon Engineers Ltd, BanerP52100034892CompletedDec 2025
- Kavya HeightsAarya Developers, WagholiP52100034815LapsedFeb 2026
- Sheetalkunj Sahakari Gruharachana Sansatha MaryaditIcon Properties, Shivaji NagarP52100034994CompletedDec 2025
- Mauli SadanMR. Ramchandra Dhondu Argade and MR. Sadashiv Uddhav Jadhav, BhosariP52100034977CompletedDec 2025
- Hyper One Phase IIUrseP52100034817LapsedDec 2023
- AmaraOrange Developers, NigdiP52100034899LapsedDec 2025
- Trimurti Commercial ComplexShree Saidatt Developers, BaramatiP52100034750CompletedDec 2023
- Prathamesh Sanskruti building of Abhinav Apartments AssociationPrathamesh Constructions, Sadashiv PethP52100034849In extensionOct 202610 months late
- Samarth HeightsHorizon Infrastructure, KiwaleP52100034746LapsedMar 2023
- Tej OneShivaji NagarP52100035004In extensionNov 20272.4 years late
- Vertica Phase 2V Realty, BalewadiP52100034995In extensionDec 20282.8 years late
- Gokhale Business Bay Phase IIGokhale Landmarks LLP, KothrudP52100034976In extensionJan 20282.0 years late
- Skyways HorizonM/s Hans Associates, LohegaonP52100034904In extensionDec 20262.0 years late
- MadhubanNG Rathi Estate, PirangutP52100034755OngoingDec 2026
- Ganga Legend Building A1Legends County Landmark Pvt Ltd, BavdhanP52100034957In extensionJun 202718 months late
- Vrindanand-BlissMakwana and Tanmay Construction, BanerP52100034827OngoingMar 2027
- Tirupati NivasS R Constructions, Dahanurkar ColonyP52100034775In extensionMay 20273.0 years late
- Lodha Pune NIBM Project-Tower 6Lodha Developers Limited, MohammadwadiP52100034751CompletedDec 2026
- Park Titan Phase IIPride Purple Infrastructure, Marunji MulshiP52100034961LapsedJun 2026
- Nivasa Enchante - Phase INivasa Associates, LohegaonP52100034898LapsedMar 2026
- TheCrownMarimagnum Constructions, UndriP52100034902LapsedSept 2025
- ParksideSapp Ventures, ErandwaneP52100034858OngoingDec 2026
- GraceTathawadeP52100034871LapsedAug 2025
- NB Crystal A Phase INanasaheb Bhintade Spacess Pvt LtdP52100034917LapsedDec 2025
- Nyati Exuberance IIINyati Builders Private Limited, MohammadwadiP52100034932CompletedJun 2025
- NB Crystal B Phase IIINanasaheb Bhintade Spacess Pvt LtdP52100034836LapsedDec 2025
- Warje Business BaySanvi Developers, Warje ChurchP52100034796OngoingMar 2027
- Sai ParadiseShree Sai Seva Developers, DehugaonP52100034909LapsedDec 2025
- Mantra Meraki Phase 6Mantra Residential Akurdi Private Limited, AkurdiP52100034965OngoingDec 2026
- Megapolis Saffron - ShopsPegasus Properties Pvt. Ltd.P52100034988CompletedDec 2024
- AvantiAmbar Developers, SangamwadiP52100035000LapsedJun 2026
- Global SpacesMDD Realty, CharholiP52100034801LapsedDec 2025
- AriseSaksham Properties, WagholiP52100034802LapsedMar 2025
- Shashi ApartmentsChaphalkar Karandikar Developers, Shivaji NagarP52100034852CompletedDec 2024
- Skyways HarmonyM/s Pranam Buildcon, LohegaonP52100034806LapsedDec 2024
- Aditya GalaxyShivaji NagarP52100034834CompletedApr 2025
- Itrend Life PlusManas Pearl Ventures, WakadP52100034723LapsedMar 2025
- Shivteerth Legacy Wing B and CShivteerth Properties, DudulgaonP52100034651LapsedMar 2026
- Easterlia Phase 2Spacemint Realty LLP, Khese ParkP52100034658CompletedDec 2025
- Empyrean - XFabriworld Structural Engineering Private Limited, CharholiP52100034660LapsedMar 2025
- Life Republic/Sector R10/10th Avenue/Universe/Phase IIIKolte-Patil Planet Real Estate Private LimitedP52100034733LapsedDec 2025
- Leela ApartmentArchway Properties, Sadashiv PethP52100034665CompletedMar 2024
- Sigma One BIZBAYFree Bird Developers LLP, SadashivpethP52100034644CompletedMar 2027
- Venkatesh PrideKiwaleP52100034664LapsedDec 2025
- Desai ResidencyDaundP52100034667LapsedFeb 2024
- Crystal VrindavanCrystal Developers, GandharvnagariP52100034649LapsedFeb 2024
- Chafa-ChampakamParvatiP52100034687LapsedJan 2024
- Phoenix ResidencyPhoenix Infraspace, Porwal ParkP52100034724DeregisteredDec 2024
- Greenfield Phase 2S N BuildconP52100034663OngoingDec 2028
- JaigadErandawaneP52100034674LapsedMar 2025
- Revell Orchid Phase V Building GLohegaonP52100034702In extensionMar 202715 months late
- L-Square PrimeLodha and Lalwani Associates, MoshiP52100034704OngoingDec 2026
- Nyati Elan Central IIIPsquare Builders LLP, WagholiP52100034714LapsedDec 2024
- Kekarav Phase IIIShrem Trading LLP, Bavdhan BudrukP52100034729In extensionDec 20263.5 years late
- DwarakadheeshPruthak Developers, WarjeP52100034648CompletedJun 2026