RERA projects in Pune district
12,486 projects are registered with MahaRERA in Pune. Of the 4,911 still under construction, 1,213 have passed the completion date their builder declared to RERA.
3,698
Ongoing, on schedule
1,213
Ongoing, past due date
5,179
Completed
2,396
Lapsed or deregistered
All projects, page 119
Showing 11,801–11,900 of 12,486, newest registrations first.
- Akshay City A and B BuildingP52100002357CompletedNov 2020
- Raajlaxmi Greens a and bShree Dharamaraj Developers, RavetP52100002102CompletedOct 2019
- Gagan Cefiro Phase 2Gagan Unnati Promoters, UndriP52100002365CompletedMar 2019
- Lotus Building A3Orient Shivam DevelopersP52100002253CompletedOct 2020
- Sunrise EnclaveSunrise RealtorsP52100002153CompletedDec 2019
- BzoneP52100002340CompletedSept 2019
- Sayama Phase 3Puranik Builders LimitedP52100002137CompletedDec 2023
- Shankeshwar Dang Ikon Phase 2Shree Shankeshwar Atharva PropertiesP52100002375CompletedDec 2021
- Sunwinds ResidentialSaniket Infrastructures, Bavdhan KhurdP52100002322CompletedDec 2019
- Guardian Wind Shire Phase 2Guardian Landmarks LLP, NandoshiP52100002080LapsedJun 2023
- Bramha Vantage CBramhacorp Limited, BavdhanP52100002254CompletedDec 2022
- Nisarg SereneAkruti BuildconP52100002312CompletedJun 2018
- Parvatara Phase 1Saakshi ConstructionsP52100002385CompletedDec 2021
- RadheyaB G Promoters and BuildersP52100002128CompletedSept 2020
- Green Glory B WingShree Mahalaxmi Group, WadgaonP52100002374CompletedSept 2021
- Bhakti Genesis D WingMahavir Constructions and Developers, Shedge WastiP52100002159CompletedSept 2018
- AnantvenkteshAnantvenkatesh Construction LLPP52100002109CompletedDec 2019
- Fortune SiddhipriyaFortune GroupP52100002108CompletedJul 2018
- Shubhankar ClassicShiv PropertiesP52100001956CompletedJan 2021
- Kingsbury Phase IJaikul Associates, CharholiP52100001994CompletedDec 2022
- Girnar 108Padmavati BuildersP52100002263CompletedOct 2019
- PiyushaP52100002284CompletedMar 2019
- Playtor Paud BPlaytor Paud Homes Private LimitedP52100001949CompletedMar 2023
- Runal ElanzaP52100002255CompletedJun 2019
- Plot No 8, Viva, PirangutPact Real Estate Private Limited, PirangutP52100002113CompletedNov 2024
- WinspireK & S AssociatesP52100002214CompletedJun 2018
- Arun ApartmentZinnia Spaces Pvt LtdP52100002034CompletedDec 2018
- Sai ShivamRahataniP52100002125CompletedSept 2018
- Saheels Fortune Park IINeev Sai AssociatesP52100002349CompletedDec 2019
- Marvel Cascada E BuildingMarvel Sigma Homes Private LimitedP52100002242LapsedApr 2022
- Snehavishwa ApartmentsSnehavishwa AssociatesP52100002326CompletedJun 2018
- Ashirwad The Living B WingAshirwad AssociatesP52100002288CompletedJul 2018
- Playtor Ranjangaon- Phase 1Playtor Lifespaces Private LimitedP52100001953CompletedDec 2017
- BellezzaSiddhishree BuildconP52100002229CompletedDec 2018
- Life Maxima Phase 1Pate Future Constructions LLP, KirkatwadiP52100002203LapsedJun 2023
- Everest PlazaChoice Developers, JadhavwadiP52100002269CompletedDec 2022
- Mayuri OptimumP52100002131CompletedJan 2021
- Sapphire GreensShreem Corporation, WaksaiP52100002171CompletedJun 2019
- Kiarah TerrazoWellwisher ApartmentP52100002327CompletedDec 2021
- Nisarg PalmsAditya Shagun DevelopersP52100002025CompletedJun 2018
- Bhalchandra PuramPolite Buildwell, RavetP52100002143CompletedDec 2020
- The OneP52100001943CompletedDec 2020
- Guru PrajaktaPraj Developers, LohegaonP52100001792CompletedMay 2019
- Marvel Isola J BuildingMarvel Landmarks Pvt Ltd, MohammadwadiP52100001843In extensionDec 20265.5 years late
- Royal OakLifestyle Developments, WakadP52100001837In extensionDec 202612 months late
- A3, Song of Joy, Geras Greensville2Gera Developments Private Limited, KharadiP52100001789CompletedJun 2019
- Valley VistaAum DevelopersP52100001854CompletedDec 2018
- Homewood 37 KondhwaP52100001675CompletedAug 2018
- Plot No. B-01 To B-21 Viva,pirangut,punePact Real Estate Private Limited, PirangutP52100001800OngoingNov 2026
- Guardian AnantamGuardian Promoters & Developers Private LimitedP52100001833LapsedDec 2022
- Marvel Sera A,b,c BuildingMarvel Sigma Homes Private LimitedP52100001878DeregisteredDec 2022
- DNV Arcelia PH 1DNV RealtyP52100001934CompletedDec 2018
- Prakruti ResidencyP52100001639LapsedJul 2018
- Kunal Aspiree Phase IIKunal Spaces Pvt Ltd, BalewadiP52100001814CompletedDec 2018
- Waters Edge Phase IVOm Sagar Developers, Pimple NilakhP52100001678CompletedMar 2018
- Renuka Gulmohar Phase IIPimpriP52100001835CompletedDec 2023
- Siddhivinayak AnganSiddhivinayak DevelopersP52100001701CompletedDec 2018
- Sarthak ShantibanSarthak & Shanti AssociatesP52100001780CompletedJun 2018
- Marvel Ganga Sangria A,B,C BuildingMarvel Landmarks Pvt LtdP52100001815CompletedDec 2019
- Sonigara LandmarkSonigara PromotersP52100001618CompletedAug 2018
- Rolling HillsShivneri AssociatesP52100001755CompletedJun 2019
- Golden Treasures Wing AP52100001868CompletedDec 2021
- Sentosa Pride Wing CShree Krishna AssociatesP52100001763CompletedJun 2018
- Dynamic GrandeurDynamic Realty EnterprisesP52100001831CompletedDec 2022
- Dreams Aryan A B wingsDreams Aryan Faltholders Association A & B, HadapsarP52100001771LapsedJun 2023
- Polite Harmony - B WingPolite Promoters & Builders, ChikhaliP52100001805CompletedDec 2020
- Amanora Adreno TowersCity Corporation Limited, Amanora Park TownP52100001822CompletedMar 2022
- NYATI ETHOS I - A1-PartNyati Builders Private Limited, UndriP52100001879DeregisteredJul 2022
- EmanateHandewadiP52100001633CompletedMar 2018
- Ratan Neptune Phase 2Ratan Housing Development LimitedP52100001790CompletedDec 2018
- UmangRanjekar RealtyP52100001862CompletedDec 2017
- Solitaire Palms EMoshiP52100001927CompletedMar 2022
- Krushnai Vihar Phase-IKrushnai Associates, ShirurP52100001766CompletedMar 2024
- Rucha Phase IIP52100001692CompletedMay 2019
- Planet9Shree Sai DevelopersP52100001880CompletedMar 2019
- Rucha Phase IP52100001941CompletedMay 2019
- Aero NestGurukrupa BuildconP52100001596CompletedMar 2019
- Dynamic OasisUndriP52100001931CompletedJun 2023
- Mantra Residency Phase 04Mantra Residencies LLP, NighojeP52100001688CompletedDec 2019
- QueenslandMoshi BoradewadiP52100001606CompletedDec 2018
- Mantra Residency Phase 02Mantra Residencies LLP, NighojeP52100001788CompletedDec 2020
- TCG Panorama Phase-II BLDG - BThe Construction & Development Company, Ambegaon BP52100001924CompletedJan 2023
- Regalia ResidencyRajheramb Properties, BavdhanP52100001872CompletedJun 2019
- Samarth NilayaShree Samarthkrupa Associates, KiwaleP52100001584CompletedJun 2019
- AMITs COLORI Phase-II H and I BuildingAmit Enterprises Housing Limited, UndriP52100001940CompletedJun 2019
- MadhukoshS R Probuild Pvt LtdP52100001643CompletedJun 2018
- Mohar PratimaMohar Housing LLP, Rao ColonyP52100001910LapsedJun 2025
- Mantra City 360 Phase02Mantra Island Homes Talegaon LLP, TalegaonP52100001834CompletedJan 2022
- ShriyogA & A AssociatesP52100001691CompletedMar 2019
- Mantra City 360 Phase01Mantra Island Homes Talegaon LLP, TalegaonP52100001846CompletedOct 2021
- Weekender Birds ViewNamrata Developers Pvt. LtdP52100001626CompletedMay 2018
- NavashishTulshibaugwale ColonyP52100001911CompletedMay 2019
- Supreme AmadoreSupreme High Spaces LLPP52100001750CompletedDec 2020
- Hazel ViewShiv Associates, HinjewadiP52100001732CompletedNov 2020
- Anika EnclaveP52100001676CompletedDec 2017
- Mantra 7 Hills Phase IVMantra Buildcrafts Private Limited, KirkatwadiP52100001757CompletedDec 2023
- Nirvana ZenNirvana DevelopersP52100001642CompletedDec 2019
- Gilt ResidencesSamrat SpacesP52100001614CompletedJun 2019
- TCG CorollaThe Construction & Development CompanyP52100001737CompletedApr 2023
- Mont Vert VivantPatel Associates, WakadP52100001586CompletedDec 2017