RERA projects in Nanded district
92 projects are registered with MahaRERA in Nanded. Of the 38 still under construction, 2 have passed the completion date their builder declared to RERA.
36
Ongoing, on schedule
2
Ongoing, past due date
37
Completed
17
Lapsed or deregistered
Most active builders
- GVC Developers5
- Msdevelopers4
- Padmavati Developers3
- Pharande Developers3
- R K Builders & Developers3
- Shagun Associates3
- Shri Swami Samarth Estates2
- Osr Infrastructure2
All projects
Showing 1–92 of 92, newest registrations first.
- Padmavati Empire Wing BPadmavati DevelopersPR1201012601592OngoingApr 2029
- Padmavati Empire B1Padmavati DevelopersPR1201012601078OngoingApr 2029
- Lotus HeightsM. M. Developers, KauthaPR1200002600473OngoingMar 2029
- Jinen SquareJinen Infra, Vip RoadPC1200002600152OngoingDec 2030
- Kuber ResidencyPR1200002600101OngoingMar 2030
- Shri Swami Samarth Heights-KauthaShri Swami Samarth EstatesPR1200002502744OngoingMar 2028
- Visawa ResidencySBG Group, Mauja WajirabadPR1200002501863OngoingJun 2028
- Palaksh ApartmentJangamwadiP51100080868OngoingMar 2028
- DeepjyotiP51100080553OngoingMar 2030
- GVC KesharbanShri Ganesh GVC Buildcon, Ganesh TalkiesP51100080491OngoingDec 2029
- Saket HeightsSaket Heights, TarodaP51100080466OngoingMar 2029
- Sanman ShikharShikhar Infra, KalamandirP51100079717OngoingDec 2029
- Anant EnclaveAnant Realty, VazirabadP51100079499OngoingDec 2027
- Padmavati EmpirePadmavati DevelopersP51100079447OngoingApr 2027
- Sai EnclaveSiddhi DevelopersP51100078770OngoingMar 2032
- Siddhi EnclaveSiddhi HomesP51100078724OngoingDec 2027
- Jaswand ApartmentPharande DevelopersP51100078002OngoingJun 2027
- Vidyasagar Park A,b and CJain Buildcon, Taroda KhurdP51100077894OngoingDec 2031
- Om residencySangam Developers, KauthaP51100077705OngoingMar 2029
- Shivneri ParkP51100077639LapsedDec 2024
- Shree Rama TownshipShree Rama Construction, Taroda BudrukP51100077486OngoingApr 2030
- Ramanuj AWadi BudrukP51100077316OngoingDec 2028
- OsrOsr Infrastructure, KauthaP51100077249CompletedSept 2024
- DaffodilDeva ConstructionsP51100077171OngoingJan 2027
- RamanujShri Tirumala Civil Work Pvt LtdP51100077007OngoingDec 2028
- Parijat ApartmentPharande Developers, Wadi BudrukP51100055847OngoingDec 2026
- Padmanabha ResidencyShree Samarth Builders and Developers, Shripad NagarP51100055704OngoingDec 2029
- Ramanuj AWadi BudrukP51100055567OngoingDec 2028
- GVC Gangadham SkyilaGVC Developers, AsarjanP51100055475OngoingDec 2028
- Prayagraj AMsdevelopers, Taroda BudrukP51100055397In extensionJun 202712 months late
- A R Khiyani CityM B Builders and Developers, VasarniP51100055045OngoingOct 2027
- GVC Siddhi SkyparkSidhi Developers, KauthaP51100054962OngoingMar 2028
- Kamal ResidencyAkruti ConstructionsP51100054294LapsedMay 2026
- GVC Saptagiri SignatureGVC Developers, KauthaP51100051931OngoingDec 2026
- Nabhangan ParkAsadullahbadP51100051043OngoingDec 2027
- Vrandawan ApartmentVisava Developers, KauthaP51100050996LapsedDec 2025
- Padmavati NagariP51100050891OngoingMar 2028
- Bharadiya TowerRaj AssociatesP51100050694CompletedAug 2025
- Shri Swami Samarth HeightsShri Swami Samarth EstatesP51100050651CompletedMar 2027
- Samartha ApartmentP51100050487OngoingAug 2028
- Krishna Kunj ResidencyShri Krishna Builders, Nanded.P51100050370CompletedFeb 2026
- Omkar AppartmentDivyaamrit Constructions India Pvt LtdP51100050016LapsedJan 2026
- Krushna KunjShri BuilderP51100050039CompletedAug 2025
- Anaika HeightsDarak Developers, VasarniP51100049655CompletedDec 2027
- Infinate OneP51100049246CompletedDec 2025
- Amrit MallDivyaamrit Constructions India Pvt Ltd, SGGS College VishnupuriP51100049117OngoingDec 2028
- GVC Shagun City IVShagun Buildcon, KauthaP51100047816CompletedDec 2025
- GVC Shagun City VShagun Buildcon, KauthaP51100047425LapsedDec 2025
- Anusaya HeightsAnusaya Heights, Harsh NagarP51100046077LapsedSept 2022
- Krupasindhu ArcadeKrupasindhu Properties, KamalnagarP51100045657OngoingMar 2028
- Krushna Nilayam ApartmentOsr InfrastructureP51100034569LapsedMar 2024
- RenukaR K Builders & Developers, Vasant NagarP51100034604CompletedDec 2024
- R R Tilak NagarR K Builders & DevelopersP51100031887CompletedDec 2023
- Raj Park TwoP51100031680LapsedMar 2024
- Mahatma Phule MarketJai Sanman Pvt Ltd, Phule MarketP51100030968LapsedAug 2025
- GVC Saptagiri Greens IIGVC Developers, KauthaP51100029308CompletedDec 2024
- Tryambkeshwar NagarRampur RaodP51100027279LapsedJun 2022
- GVC Shagun ParkGVC DevelopersP51100026549LapsedJun 2024
- Manthan ParkUnited BuildconP51100026409In extensionMar 20296.5 years late
- GVC Shagun City Phase IIIShagun Associates, KauthaP51100026123CompletedJun 2024
- LapsedOct 2023
- Shri Govindraj ResidencyShri Govindraj Construction, KauthaP51100024429CompletedDec 2024
- Raj Villa GP51100023920LapsedDec 2020
- Shri ApartmentKK Builders & Developers, Taroda KhurdP51100022944LapsedJun 2022
- Gokuldham City Part ARama DevelopersP51100020534OngoingDec 2030
- GVC Gangadham Phase IGVC Developers, AsarjanP51100018353CompletedMar 2022
- GVC Shagun City Phase IIShagun Associates, KauthaP51100017950CompletedDec 2022
- BhaghyateerthP51100016614CompletedMar 2022
- Raghunath NagarR K Builders & DevelopersP51100015354CompletedDec 2023
- GVC Shagun City Phase 1Shagun Associates, KauthaP51100015116CompletedDec 2022
- Sanman WoodsJai Kedarnath EnterprisesP51100014290CompletedJul 2019
- K K HeightsK K DevelopersP51100014171CompletedDec 2023
- Krupasindhu TowerKrupasindhu PropertiesP51100013244CompletedDec 2022
- D L InfraP51100013123CompletedSept 2019
- Raj ParkP51100012601CompletedOct 2019
- Paldewar CityP51100012289CompletedJul 2024
- Raj Commercial Cum Residentail Building G -FP51100012323CompletedMar 2019
- Sai HeightsM/s Jinen DevelopersP51100012167CompletedDec 2021
- Apurv PlazaMsdevelopersP51100010599CompletedJul 2018
- Kasliwal Kadam HeightsKasliwal ConstructionsP51100007821LapsedDec 2021
- Vishwakarma LayoutVishwakarma Housing Pvt. LtdP51100008307LapsedDec 2023
- Kasliwal Infra ProjectsKasliwal Infra Projects, TilaknagarP51100007666LapsedDec 2023
- Parwati SadanMsdevelopersP51100006423CompletedJul 2019
- Raj Residency HP51100006613CompletedOct 2018
- Digambar SadanMsdevelopersP51100006594CompletedDec 2019
- Laijai NagariKamlesh BachewarP51100005371CompletedDec 2021
- Tulsi DevelopersTulsi DevelopersP51100005078CompletedMar 2018
- Center park residencyP51100003870CompletedDec 2021
- SaptagiriSaptagiri DevelopersP51100002999CompletedJan 2018
- Laijai Nagari 14/a/1Kamlesh BachewarP51100002964CompletedDec 2021
- Pharande ParkPharande DevelopersP51100002286CompletedMar 2022
- Vithai ApartmentsAmar ConstructiosP51100002164CompletedAug 2018