RERA projects in Jalgaon district
200 projects are registered with MahaRERA in Jalgaon. Of the 23 still under construction, 5 have passed the completion date their builder declared to RERA.
18
Ongoing, on schedule
5
Ongoing, past due date
132
Completed
45
Lapsed or deregistered
Most active builders
- Shree N T Mundada Park4
- Patil Mahajan3
- Jain Buildcon3
- Arihant Developers3
- M/s Shree Swami Samarth Traders Builders and Developers3
- Parakh Plexus Realty Ltd.3
- Raka Constructions2
- N & L Associates2
All projects
Showing 1–100 of 200, newest registrations first.
- Gauri Nandan ApartmentPatil Mahajan, SatarePM1130002600438OngoingDec 2028
- One High StreetAshtavinayak Enterprises, MidcP49900081002OngoingOct 2026
- The Lake ParadiseJivraj Buildcon, Mehrun ShivarP49900080789OngoingMar 2027
- Krushna HeightsM/s Shree Swami Samarth Traders Builders and Developrs, ChalisgaonP49900079040LapsedAug 2025
- Casa De RoyaleRaka Constructions, BhusawalP49900078963OngoingDec 2027
- Samarths SuvruddhiSamarth Constrowell Private Limited, Adarsh Nagar MehrunP49900078387OngoingMar 2029
- JK EleganceJK Elegance, Ganpati NagarP49900077935OngoingMay 2027
- Laxmi HeightsSatare ShivarP49900077768OngoingDec 2027
- Ajinkyatara AppartmentPost ChalisgaonP49900077344LapsedDec 2025
- Majestique LandmarkOrnate Properties, Mehrun ShivarP49900076967OngoingSept 2026
- Sai Charan ResidencyN & L Associates, Meharun ShivarP49900076732LapsedJun 2026
- AntarikshMehrun Lake AreaP49900056200OngoingDec 2026
- Om ResidencyJalgaon Projects Pvt LtdP49900056006In extensionSept 202612 months late
- Krushnaji ArcadeM/s. Shreyash Realties, Sambhaji ChowkP49900055715OngoingJan 2028
- Mundada High StreetMundada Realty, AmalnerP49900054562CompletedApr 2026
- Sukruti SuratnaSuratna Infra LLPP49900052357CompletedApr 2027
- VighnarajPatil Mahajan, Moje Satare BhusawalP49900051886CompletedFeb 2025
- Rupchand Ramchand ComplexP49900051674CompletedJan 2028
- Shiv NamanJain Buildcon, Shiv ColonyP49900051276LapsedMar 2025
- Shiv Maan HeightsJain Infra, Julalsing WadiP49900051360LapsedMar 2026
- SSD ComplexJay Narayan Developers, ChalisgaonP49900050851In extensionOct 20262.1 years late
- Anvika ArcadeP49900050721LapsedJun 2025
- Sai Prakash HeightsJain BuildconP49900050466CompletedDec 2024
- PPRL Basera - JaynagarBodwadP49900050211In extensionDec 202612 months late
- Pride ResidencySatare ShivarP49900050252LapsedDec 2024
- Vastu VandanShanti NagarP49900050025LapsedJul 2025
- Gokuldas HousingGokuldas Housing, Indiratai NagarP49900049845LapsedDec 2025
- Vastu NinePride Leela Builders and DevelopersP49900049700CompletedDec 2025
- VrindavanRaka Constructions, BhusawalP49900049558CompletedDec 2025
- Bhagavanti HeightsShiv Gajanan Construction, Mehrun ShivarP49900049012CompletedOct 2024
- Sai Krushanasha HeightSai Krushna Associates, Savkhede BudrukP49900049006CompletedMar 2025
- Udyog IshwarM/s. Faith Build Constructions, JalgoanP49900048617OngoingDec 2027
- Vasant ViharAaradhya InfraprojectsP49900048286CompletedDec 2023
- Shri Gajanan ComplexSwami Samarth NagarP49900048149LapsedDec 2025
- M SquareAaradhya InfraprojectsP49900048046OngoingDec 2027
- Morya PlazaTrimurti Contructions, ErandolP49900047798LapsedMar 2026
- Omkara ResidencyJalgaon Projects Pvt LtdP49900046617CompletedMar 2025
- Sahyadri ShikharSahyadri ShikharP49900046427LapsedSept 2024
- Ganpati NagarGiriraj Developers, PahiladP49900046017CompletedMar 2025
- Shivnery ParkSuperealty Buildcon LLP, ChalisgaonP49900045804OngoingDec 2026
- Sukruti CentrumArihant ConstructionP49900045542CompletedMar 2025
- Suryadarshan ResidencyGanesh Gopal Chaudhari, Pimprala ShivarP49900045489LapsedMar 2025
- Chhoriya Fortune City -Parola plottingAnmol Chhoriya and Associates, Bus StandP49900045424CompletedDec 2029
- Sunshine TowerAmalnerP49900045331CompletedDec 2025
- Arihannt SapphireArihannt SapphireP49900034912LapsedMar 2026
- JK PrideJaju & Khandelwal Constructions, Pimprala ShivarP49900034265CompletedDec 2024
- Mannat heightsBhusawalP49900034024LapsedDec 2023
- Shambho ResidencyChalisgaonP49900033889LapsedDec 2024
- Aarohi HeightsNimkhedi KDP49900033970LapsedDec 2024
- Jamuna ResidencyJamuna Infra, SavkhedaP49900033786LapsedJun 2025
- Shivaay SquareIshanavi Construtech Pvt Ltd, MehrunP49900032755CompletedAug 2023
- Sukruti SerenityArihant Developers, Mehrun ShivarP49900032651CompletedDec 2024
- Park RoyaleMahaveer Buildcon, Collector Bunglow AreaP49900032274CompletedDec 2024
- Morya HeightMorya Builders and DevelopersP49900032260CompletedMar 2024
- Shree Swami Samarth SankulKadam and Patil Developers, ChopdaP49900031124CompletedMar 2023
- Varad HeightsToke and Dhake Associates, Vivekanand NagarP49900031133CompletedAug 2026
- Sai DhamJB AssociatesP49900031041OngoingAug 2026
- Navkar HeightsRajesh Construction and BuildersP49900031018CompletedJun 2030
- Ramai Keshav Vihar Phase 3SatareP49900030872CompletedDec 2023
- Navkar ResidencyGlobal Builders, Karjai RoadP49900030637OngoingAug 2026
- PrabhulilaVastu Builders, Raisoni NagarP49900030722CompletedDec 2023
- Kamlai ResidencyShiv ColonyP49900030608LapsedJun 2024
- Mundada EstateAmalnerP49900030529CompletedDec 2023
- Shree Balaji PrideShree Balaji Developers, ChopdaP49900030174LapsedDec 2022
- Swami Apartment 2ChopdaP49900030162LapsedMar 2023
- Laxman AvenueChanda Gauri NagarP49900029456LapsedApr 2022
- RadhakrishnaShankheshwar Associates, Shivaji NagarP49900029291CompletedMar 2024
- Sai JyotsnaiV B Wani and CompanyP49900029283LapsedDec 2023
- New Anand KrushnaM/s Shree Swami Samarth Traders Builders and Developers, ChalisgaonP49900029087CompletedJun 2023
- Sai KrushanashaSai Krushna Associates, Savkhede ShivarP49900028510CompletedSept 2022
- Shobharam HeightsShriram Construction, Pimprala ShivarP49900027585LapsedSept 2022
- Ramai Keshav Vihar Phase-2BhusawalP49900027325CompletedMar 2023
- Sinhagadh Villas Phase ISavkhede BudrukP49900027082CompletedSept 2022
- Patil HeightsJuna SatareP49900027033CompletedDec 2024
- ShubhamRajeshwar NagarP49900026547CompletedJun 2023
- Gopal Krushna Residency Phase 2Thepade Builders, Bhadgaon RoadP49900026527LapsedSept 2024
- TulasWanjola RoadP49900026363CompletedJun 2023
- Sayed Zahidali JamataliJammohalla BhusawalP49900026094LapsedMar 2024
- Shri Krishna AvenueP49900025829CompletedJun 2022
- Aditya HeightsVivekanand NagarP49900025748In extensionMar 20274.8 years late
- Kunal ParkM/s Shree Swami Samarth Traders Builders and Developers, ChalisgaonP49900025731CompletedAug 2023
- Shri ApartmentBhusawalP49900025722LapsedSept 2023
- Shivtirth ApartmentRaisony NagarP49900025719CompletedSept 2022
- Mangalam ParkMangalam Infra, PachoraP49900025679In extensionSept 20285.0 years late
- Krupa ApartmentMehrunP49900025629CompletedJun 2022
- Sai Yash HeightsJain Buildcon, Ganesh ColonyP49900025533CompletedSept 2022
- Swami Pushpa ApartmentP49900025509CompletedDec 2022
- Ganesha ChaitanyaP49900025428CompletedMar 2024
- Ganesha DivineGurudatta Global Developers, Ashababa NagarP49900025389CompletedJun 2024
- Nayantara Arcade City PrideNayantara Developers, Govinda Rikshaw StopP49900025324CompletedJun 2025
- Vandan HeightsP49900025302LapsedMar 2022
- Shreeram ResidencyDandekar NagarP49900025239CompletedMar 2021
- Shakuntala HeightsShiv Construction, Pimprala ShivarP49900025213CompletedMar 2022
- Ramai Keshav Vihar Phase-1BhusawalP49900024375LapsedJan 2023
- Labhoni Kamal VillaGanesh WadiP49900024167LapsedMar 2023
- R D TowerM/s Shree Swami Samarth Traders Builders and Developers, ChalisgaonP49900023945CompletedDec 2022
- Shri Sai ViharSuresh NagarP49900023896CompletedDec 2020
- Moreshwar ApartmentPatil MahajanP49900023884LapsedDec 2023
- Shakun EstatesP49900023842CompletedJun 2023
- Behede Deshpande ComplexBehede & Deshpande Group, ChopdaP49900023583CompletedDec 2023