Dev Ellanza
A others project by DLS Enterprises in TITWALA, Thane.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- DLS Enterprises · Partnership
- Project type
- Others
- Land area
- 2,500 m² · Permissible built-up (FSI) 7,881 m²
- Total units
- 117 across 1 wing
- Estimated cost
- ₹20.3 Cr
- Parking
- 185 four-wheeler · 18 two-wheeler
- Application date
- 23 Oct 2022
1 wing
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 15 of 15 proposed | 117 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- VIJAY PANDEY & ASSOCIATES · CA/96/20081
- Structural engineer
- Ram V Marathe · STATE/R/2024/APL/09587
- Project bank
- HDFC BANK
Where it sits
TITWALA, Thane — 421605.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Dev Ellanza: common questions
Is Dev Ellanza RERA registered?
Yes. Dev Ellanza is registered with MahaRERA under registration number P51700048647, granted on 10 January 2023. As of July 2026, the registration is active under a MahaRERA extension.
What is the possession date of Dev Ellanza?
The developer has declared completion by April 2027 in its MahaRERA filing, revised from the original April 2026. The record shows the project running 365 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Dev Ellanza?
Dev Ellanza is developed by DLS Enterprises, the promoter named in its MahaRERA registration.
Where is Dev Ellanza located?
Dev Ellanza is in Titwala, Thane (PIN 421605), Maharashtra, as declared in its RERA registration.
How many units does Dev Ellanza have, and how many are sold?
Dev Ellanza has 117 units on its RERA registration. 32 were reported sold as of July 2026, leaving 85 unsold.
How much construction of Dev Ellanza is complete?
By the developer's own quarterly filing, 55% of the work is done, measured against the project's cost estimate.
Is there any litigation against Dev Ellanza?
No litigation is declared on Dev Ellanza's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Titwala
- Raj Vaibhav Park · Thane
- Ashlar Tattva B Wing · Thane
- Adwait Avanya · Thane
- Sai Arcade · Thane
- Sai Mauli Phase - II · Thane
- The Nilaya · Thane
- Mantra · Thane
- Ramkrishna Heights · Thane