Datta Enclave
A residential / group housing project by Avs Realty in PASHAN, Pune.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Avs Realty · Partnership
- Project type
- Residential / Group Housing
- Land area
- 1,417 m² · Permissible built-up (FSI) 4,215 m²
- Total units
- 70 across 4 wings
- Estimated cost
- ₹8.2 Cr
- Land ownership
- Promoter is the landowner
- Parking
- 6 four-wheeler · 74 two-wheeler
- Application date
- 11 Jun 2024
4 wings across 4 buildings
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 5 of 5 proposed | 10 |
| NA | 5 of 5 proposed | 10 |
| NA | 5 of 5 proposed | 10 |
| NA | 7 of 7 proposed | 40 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- Group Consultants · CA/2002/28913
- Structural engineer
- PG Structural Consultants
- Project bank
- ICICI BANK LIMITED
Where it sits
PASHAN, Pune — 411021.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Datta Enclave: common questions
Is Datta Enclave RERA registered?
Yes. Datta Enclave is registered with MahaRERA under registration number P52100077601, granted on 15 October 2024. As of July 2026, the registration is active.
What is the possession date of Datta Enclave?
The developer has declared completion by March 2029 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Datta Enclave?
Datta Enclave is developed by Avs Realty, the promoter named in its MahaRERA registration.
Where is Datta Enclave located?
Datta Enclave is in Pashan, Pune (PIN 411021), Maharashtra, as declared in its RERA registration.
How many units does Datta Enclave have, and how many are sold?
Datta Enclave has 70 units on its RERA registration. 53 were reported sold as of July 2026, leaving 17 unsold.
How much construction of Datta Enclave is complete?
By the developer's own quarterly filing, 88% of the work is done, measured against the project's cost estimate.
Is there any litigation against Datta Enclave?
No litigation is declared on Datta Enclave's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Pashan
- Livience Aleenta Phase III · Pune
- Shiv Srushti · Pune
- 51 Midtown · Pune
- The Lords Part 3 · Pune
- The Lords Part 2 · Pune
- The Lords Part 1 · Pune
- M Soul Strings Wing B · Pune
- M Soul Strings Wing C · Pune