Status & progress
Per MahaRERA record as of Sept 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Continental Sidhant Reality · Partnership
- Project type
- Residential / Group Housing
- Land area
- 13,250 m² · Permissible built-up (FSI) 18,575 m²
- Total units
- 286 across 3 wings
- Estimated cost
- ₹60 Cr
- Land ownership
- Promoter is the landowner
- Parking
- 39 four-wheeler · 168 two-wheeler
- Held outside open sale
- 48 landowner/investor share
- Application date
- 29 Mar 2018
3 wings
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 11 of 11 proposed | 66 |
| NA | 15 of 15 proposed | 109 |
| NA | 15 of 15 proposed | 111 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- APICES STUDIO PRIVATE LIMITED · CA/96/20591
- Structural engineer
- EPICONS CONSULTANT PVT LTD · STATE/R/2022/APL/01944
- Project bank
- HDFC BANK
Where it sits
KON GAON, Thane — 421302.
1 flag on this project
What they are and why they matter — in the full report.
Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.
Unlock full report — ₹99Why these flags matter
Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.
Unlock full report — ₹99Complaints, litigation & charges
Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.
Unlock full report — ₹99Continental Futura: common questions
Is Continental Futura RERA registered?
Yes. Continental Futura is registered with MahaRERA under registration number P51700015939, granted on 9 April 2018. As of September 2026, the registration is active under a MahaRERA extension.
What is the possession date of Continental Futura?
The developer has declared completion by March 2028 in its MahaRERA filing, revised from the original March 2024. The record shows the project running 1462 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Continental Futura?
Continental Futura is developed by Continental Sidhant Reality, the promoter named in its MahaRERA registration.
Where is Continental Futura located?
Continental Futura is in Kon Gaon, Thane (PIN 421302), Maharashtra, as declared in its RERA registration.
How many units does Continental Futura have, and how many are sold?
Continental Futura has 286 units on its RERA registration. 134 were reported sold as of September 2026, leaving 152 unsold.
How much construction of Continental Futura is complete?
By the developer's own quarterly filing, 41% of the work is done, measured against the project's cost estimate.
Is there any litigation against Continental Futura?
No litigation is declared on Continental Futura's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Kon Gaon
- Sai Darshan D Wing · Thane
- Prince Avenue · Thane
- Pehla Ghar - Divekar Complex · Thane
- Irasa Greens · Thane
- Saniya Heights · Thane
- Maitri Icon · Thane
- Utsav · Thane
- Nandai Residency · Thane