ActiveP51700034243Registered Mar 2022No active red flags

Central Park

A others project by Harmain Enterprises in KAUSA, MUMBRA, Thane.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
20%
cost-weighted
Declared completion
Dec 2027
no delay on record
Units sold
5 / 639
1% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Harmain Enterprises · Partnership
Project type
Others
Land area
9,591 m² · Permissible built-up (FSI) 6,578 m²
Total units
639 across 3 wings
Estimated cost
₹136.1 Cr
Application date
15 Mar 2022
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA16 of 16 proposed244
NA16 of 16 proposed196
NA16 of 16 proposed199
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
RIGHTANGLE ARCHITECT & INTERIOR DESIGNERS · CA/2010/47370
Structural engineer
SSCONS CONSULTING STRUCTURAL ENGINEERS
Project bank
BANK OF BARODA
Location

Where it sits

KAUSA, MUMBRA, Thane — 400612.

Locality
KAUSA, MUMBRA
District
Thane
Authority
Thane Municipal Corporation
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Central Park: common questions

Is Central Park RERA registered?

Yes. Central Park is registered with MahaRERA under registration number P51700034243, granted on 25 March 2022. As of July 2026, the registration is active.

What is the possession date of Central Park?

The developer has declared completion by December 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Central Park?

Central Park is developed by Harmain Enterprises, the promoter named in its MahaRERA registration.

Where is Central Park located?

Central Park is in Mumbra, Thane (PIN 400612), Maharashtra, as declared in its RERA registration.

How many units does Central Park have, and how many are sold?

Central Park has 639 units on its RERA registration. 332 were reported sold as of July 2026, leaving 307 unsold.

How much construction of Central Park is complete?

By the developer's own quarterly filing, 20% of the work is done, measured against the project's cost estimate.

Is there any litigation against Central Park?

No litigation is declared on Central Park's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Mumbra