Central Meadows
A residential / group housing project by Honour Realty in MUMBRA, Thane.
Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗
Status & progress
Per MahaRERA record as of Jul 2026.
Project basics
As filed with MahaRERA — not analysis, just the record.
- Promoter
- Honour Realty · Partnership
- Project type
- Residential / Group Housing
- Land area
- 3,998 m² · Permissible built-up (FSI) 12,605 m²
- Total units
- 143 across 5 wings
- Estimated cost
- ₹28.2 Cr
- Application date
- 23 Aug 2023
5 wings across 5 buildings
Floors and unit counts as filed.
| Wing | Floors sanctioned | Total units |
|---|---|---|
| NA | 8 of 8 proposed | 59 |
| NA | 8 of 8 proposed | 28 |
| NA | 8 of 8 proposed | 28 |
| NA | 4 of 4 proposed | 16 |
| NA | 4 of 4 proposed | 12 |
Promoter & professionals
Names and registrations as declared — no background analysis.
- Architect
- RIGHT ANGLE · CA/2010/47370
- Structural engineer
- SS CONS CONSULTING STRUCTURAL ENGINEERS · TMCB/R/2024/APL00325
- Project bank
- AXIS BANK
Where it sits
MUMBRA, Thane — 400612.
No active red flags
Absence of a flag reflects the record as filed, not an assessment of safety.
Central Meadows: common questions
Is Central Meadows RERA registered?
Yes. Central Meadows is registered with MahaRERA under registration number P51700053134, granted on 16 October 2023. As of July 2026, the registration is active.
What is the possession date of Central Meadows?
The developer has declared completion by December 2027 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.
Who is the builder of Central Meadows?
Central Meadows is developed by Honour Realty, the promoter named in its MahaRERA registration.
Where is Central Meadows located?
Central Meadows is in Mumbra, Thane (PIN 400612), Maharashtra, as declared in its RERA registration.
How many units does Central Meadows have, and how many are sold?
Central Meadows has 143 units on its RERA registration. 75 were reported sold as of July 2026, leaving 68 unsold.
How much construction of Central Meadows is complete?
By the developer's own quarterly filing, 25% of the work is done, measured against the project's cost estimate.
Is there any litigation against Central Meadows?
No litigation is declared on Central Meadows's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.
More RERA projects in Mumbra
- Sky Valley - Phase 2 · Thane
- Mek Grand Central · Thane
- Ocean Green · Thane
- Grand Meridian City · Thane
- Harmain Tower · Thane
- Prince Tower · Thane
- Elite Tower · Thane
- Nice World 2 · Thane