In ExtensionP51800009838Registered Aug 2017Delayed 1826dExtension1 red flag

Biz Point

A commercial project by N N Datar & Associates in KURLA, Mumbai Suburban.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
106%
cost-weighted
Declared completion
Dec 2027
delayed 1826d
Units sold
38 / 111
34% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
N N Datar & Associates · Partnership
Project type
Commercial
Land area
866 m² · Permissible built-up (FSI) 5,455 m²
Total units
111 across 1 wing
Estimated cost
₹35.8 Cr
Application date
31 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA17 of 17 proposed111
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
DEOLE BROS · 840005323
Structural engineer
SHRIKHANDE CONSULTANCY
Project bank
KARNATAKA BANK LIMITED
Location

Where it sits

KURLA, Mumbai Suburban — 400086.

Locality
KURLA
District
Mumbai Suburban
Authority
Municipal Corporation of Greater Mumbai
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Biz Point: common questions

Is Biz Point RERA registered?

Yes. Biz Point is registered with MahaRERA under registration number P51800009838, granted on 22 August 2017. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Biz Point?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original December 2022. The record shows the project running 1826 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Biz Point?

Biz Point is developed by N N Datar & Associates, the promoter named in its MahaRERA registration.

Where is Biz Point located?

Biz Point is in Kurla, Mumbai (PIN 400086), Maharashtra, as declared in its RERA registration.

How many units does Biz Point have, and how many are sold?

Biz Point has 111 units on its RERA registration. 49 were reported sold as of July 2026, leaving 62 unsold.

How much construction of Biz Point is complete?

By the developer's own quarterly filing, 106% of the work is done, measured against the project's cost estimate.

Is there any litigation against Biz Point?

No litigation is declared on Biz Point's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.