Per MahaRERA record as of Jul 2026.

Construction
23%
cost-weighted
Declared completion
Dec 2028
no delay on record
Units sold
26 / 673
4% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Dhanveer Enterprises · Partnership
Project type
Residential / Group Housing
Land area
8,750 m² · Permissible built-up (FSI) 41,332 m²
Total units
673 across 3 wings
Estimated cost
₹196 Cr
Land ownership
Promoter is the landowner
Parking
147 four-wheeler · 0 two-wheeler
Held outside open sale
49 landowner/investor share · 39 reserved
Application date
28 Mar 2024
Buildings & units

3 wings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA14 of 14 proposed157
NA14 of 14 proposed157
NA8 of 8 proposed359
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Sthapatya Nirmaan Civil & Architectural Services · CA/99/24527
Structural engineer
Sahil Raju Bana
Project bank
RBL Bank Limited
Location

Where it sits

Dombivli, Thane — 421204.

Locality
Dombivli
District
Thane
Authority
Kalyan Dombivali Municipal Corporation
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Balaji Uphomes: common questions

Is Balaji Uphomes RERA registered?

Yes. Balaji Uphomes is registered with MahaRERA under registration number P51700055656, granted on 5 April 2024. As of July 2026, the registration is active.

What is the possession date of Balaji Uphomes?

The developer has declared completion by December 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Balaji Uphomes?

Balaji Uphomes is developed by Dhanveer Enterprises, the promoter named in its MahaRERA registration.

Where is Balaji Uphomes located?

Balaji Uphomes is in Dombivli, Thane (PIN 421204), Maharashtra, as declared in its RERA registration.

How many units does Balaji Uphomes have, and how many are sold?

Balaji Uphomes has 673 units on its RERA registration. 131 were reported sold as of July 2026, leaving 542 unsold.

How much construction of Balaji Uphomes is complete?

By the developer's own quarterly filing, 23% of the work is done, measured against the project's cost estimate.

Is there any litigation against Balaji Uphomes?

No litigation is declared on Balaji Uphomes's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.