ActivePM1260002501135Registered Oct 2025No active red flags

Awadh One

A mixed project by M/s GPL SANKALP GROUP in -, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
8%
cost-weighted
Declared completion
Apr 2029
no delay on record
Units sold
4 / 24
17% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
M/s GPL SANKALP GROUP · Partnership
Project type
Mixed
Land area
2,504 m² · Permissible built-up (FSI) 7,544 m²
Total units
24 across 1 wing
Estimated cost
₹24.5 Cr
Parking
87 four-wheeler · 247 two-wheeler
Application date
01 Oct 2025
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA7 of 7 proposed24
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
· CA/98/22909
Structural engineer
· JIPSI/BANKHA 1/923
Project bank
THE COSMOS CO OPERATIVE BANK LIMITED
Location

Where it sits

-, Pune — 411058.

Locality
-
District
Pune
Authority
PUNE MUNICIPAL CORPORATION
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Awadh One: common questions

Is Awadh One RERA registered?

Yes. Awadh One is registered with MahaRERA under registration number PM1260002501135, granted on 9 October 2025. As of July 2026, the registration is active.

What is the possession date of Awadh One?

The developer has declared completion by April 2029 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Awadh One?

Awadh One is developed by M/s GPL Sankalp Group, the promoter named in its MahaRERA registration.

Where is Awadh One located?

Awadh One is in Pune (PIN 411058), Maharashtra, as declared in its RERA registration.

How many units does Awadh One have, and how many are sold?

Awadh One has 24 units on its RERA registration. 4 were reported sold as of July 2026, leaving 20 unsold.

How much construction of Awadh One is complete?

By the developer's own quarterly filing, 8% of the work is done, measured against the project's cost estimate.

Is there any litigation against Awadh One?

No litigation is declared on Awadh One's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.