In ExtensionP51800004402Registered Aug 2017Delayed 2009dExtension2 red flags

Avenue Wing B

A residential / group housing project by Dharmesh Constructions Private Limited in Kandivali, Mumbai Suburban.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
58%
cost-weighted
Declared completion
Dec 2026
delayed 2009d
Units sold
111 / 174
64% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Dharmesh Constructions Private Limited · Company
Project type
Residential / Group Housing
Land area
698 m² · Permissible built-up (FSI) 14,280 m²
Total units
174 across 1 wing
Estimated cost
₹64.1 Cr
Land ownership
Promoter is the landowner
Application date
29 Jul 2017
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA28 of 28 proposed174
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Mr.RAJESH ATHA · 88 / 11447
Structural engineer
SACPL, Mr Nikhil sanghvi. · STR/S/193
Project bank
HDFC BANK
Location

Where it sits

Kandivali, Mumbai Suburban — 400067.

Locality
Kandivali
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority
Red flags

2 flags on this project

What they are and why they matter — in the full report.

Unlock the 2 red flags on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Avenue Wing B: common questions

Is Avenue Wing B RERA registered?

Yes. Avenue Wing B is registered with MahaRERA under registration number P51800004402, granted on 9 August 2017. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Avenue Wing B?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original June 2021. The record shows the project running 2009 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Avenue Wing B?

Avenue Wing B is developed by Dharmesh Constructions Private Limited, the promoter named in its MahaRERA registration.

Where is Avenue Wing B located?

Avenue Wing B is in Kandivali, Mumbai (PIN 400067), Maharashtra, as declared in its RERA registration.

How many units does Avenue Wing B have, and how many are sold?

Avenue Wing B has 174 units on its RERA registration. 153 were reported sold as of July 2026, leaving 21 unsold.

How much construction of Avenue Wing B is complete?

By the developer's own quarterly filing, 58% of the work is done, measured against the project's cost estimate.

Is there any litigation against Avenue Wing B?

2 litigation cases are declared on Avenue Wing B's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Kandivali

All RERA projects in Kandivali →

Other projects by Dharmesh Constructions Private Limited

All projects by Dharmesh Constructions Private Limited →