In ExtensionP52100026792Registered Oct 2020Delayed 730dExtension1 red flag

Ambrosia Alley

A residential / group housing project by Ambrosia Landmark Private Limited in NR DSK Sundarbun, Pune.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
100%
cost-weighted
Declared completion
Jun 2027
delayed 730d
Units sold
44 / 74
59% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Ambrosia Landmark Private Limited · Company
Project type
Residential / Group Housing
Land area
4,000 m² · Permissible built-up (FSI) 7,765 m²
Total units
74 across 1 wing
Estimated cost
₹26.1 Cr
Land ownership
Promoter is the landowner
Parking
46 four-wheeler · 31 two-wheeler
Held outside open sale
30 landowner/investor share
Application date
21 Oct 2020
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA16 of 16 proposed74
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Dnyaneshwar Birajdar · 1
Structural engineer
Dattatray Gorakshnath Mate
Project bank
UNION BANK OF INDIA
Location

Where it sits

NR DSK Sundarbun, Pune — 411028.

Locality
NR DSK Sundarbun
District
Pune
Authority
a
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Ambrosia Alley: common questions

Is Ambrosia Alley RERA registered?

Yes. Ambrosia Alley is registered with MahaRERA under registration number P52100026792, granted on 25 October 2020. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Ambrosia Alley?

The developer has declared completion by June 2027 in its MahaRERA filing, revised from the original June 2025. The record shows the project running 730 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Ambrosia Alley?

Ambrosia Alley is developed by Ambrosia Landmark Private Limited, the promoter named in its MahaRERA registration.

Where is Ambrosia Alley located?

Ambrosia Alley is in Pune (PIN 411028), Maharashtra, as declared in its RERA registration.

How many units does Ambrosia Alley have, and how many are sold?

Ambrosia Alley has 74 units on its RERA registration. 44 were reported sold as of September 2026, leaving 30 unsold.

How much construction of Ambrosia Alley is complete?

By the developer's own quarterly filing, 100% of the work is done, measured against the project's cost estimate.

Is there any litigation against Ambrosia Alley?

No litigation is declared on Ambrosia Alley's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.