In ExtensionP51700028707Registered Mar 2021Delayed 1280dExtension1 red flag

Al Amin Tower

A residential / group housing project by S V Builders in BHIWANDI, Thane.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
92%
cost-weighted
Declared completion
Dec 2026
delayed 1280d
Units sold
16 / 40
40% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
S V Builders · Partnership
Project type
Residential / Group Housing
Land area
796 m² · Permissible built-up (FSI) 900 m²
Total units
40 across 1 wing
Estimated cost
₹4 Cr
Land ownership
Promoter is the landowner
Parking
0 four-wheeler · 12 two-wheeler
Application date
10 Mar 2021
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA5 of 5 proposed40
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
NAKHUDA ASSOCIATES · TP/ARCH/39
Structural engineer
EBAD ASSOCIATES
Project bank
HDFC BANK
Location

Where it sits

BHIWANDI, Thane — 421302.

Locality
BHIWANDI
District
Thane
Authority
BNCMC
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Al Amin Tower: common questions

Is Al Amin Tower RERA registered?

Yes. Al Amin Tower is registered with MahaRERA under registration number P51700028707, granted on 25 March 2021. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of Al Amin Tower?

The developer has declared completion by December 2026 in its MahaRERA filing, revised from the original June 2023. The record shows the project running 1280 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Al Amin Tower?

Al Amin Tower is developed by S V Builders, the promoter named in its MahaRERA registration.

Where is Al Amin Tower located?

Al Amin Tower is in Bhiwandi, Thane (PIN 421302), Maharashtra, as declared in its RERA registration.

How many units does Al Amin Tower have, and how many are sold?

Al Amin Tower has 40 units on its RERA registration. 16 were reported sold as of September 2026, leaving 24 unsold.

How much construction of Al Amin Tower is complete?

By the developer's own quarterly filing, 92% of the work is done, measured against the project's cost estimate.

Is there any litigation against Al Amin Tower?

No litigation is declared on Al Amin Tower's MahaRERA record as of September 2026. A clean record reflects what was filed, not a legal title check.