ActiveP51800054477Registered Jan 2024No active red flags

Aaradhya Onepark

A residential / group housing project by Micl Creators LLP in GHATKOPAR EAST, Mumbai Suburban.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
43%
cost-weighted
Declared completion
Jul 2028
no delay on record
Units sold
105 / 468
22% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Micl Creators LLP · Others
Project type
Residential / Group Housing
Land area
13,128 m² · Permissible built-up (FSI) 66,070 m²
Total units
468 across 11 wings
Estimated cost
₹387.8 Cr
Land ownership
Promoter is the landowner
Parking
945 four-wheeler · 0 two-wheeler
Held outside open sale
222 rehab
Application date
05 Jan 2024
Buildings & units

11 wings across 11 buildings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA20 of 20 proposed14
NA22 of 22 proposed52
NA22 of 22 proposed32
NA22 of 22 proposed52
NA22 of 22 proposed32
NA22 of 22 proposed34
NA22 of 22 proposed49
NA22 of 22 proposed69
NA22 of 22 proposed50
NA22 of 22 proposed33
NA22 of 22 proposed51
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
KALPESH L SHAH · 5/507/LS
Structural engineer
J W CONSULTANTS LLP · BMC/STR/W/10
Project bank
ICICI BANK LIMITED
Location

Where it sits

GHATKOPAR EAST, Mumbai Suburban — 400077.

Locality
GHATKOPAR EAST
District
Mumbai Suburban
Authority
P-16663/2023)/N Ward/FP/CC/1/New
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Aaradhya Onepark: common questions

Is Aaradhya Onepark RERA registered?

Yes. Aaradhya Onepark is registered with MahaRERA under registration number P51800054477, granted on 25 January 2024. As of July 2026, the registration is active.

What is the possession date of Aaradhya Onepark?

The developer has declared completion by July 2028 in its MahaRERA filing. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Aaradhya Onepark?

Aaradhya Onepark is developed by Micl Creators LLP, the promoter named in its MahaRERA registration.

Where is Aaradhya Onepark located?

Aaradhya Onepark is in Ghatkopar East, Mumbai (PIN 400077), Maharashtra, as declared in its RERA registration.

How many units does Aaradhya Onepark have, and how many are sold?

Aaradhya Onepark has 468 units on its RERA registration. 124 were reported sold as of July 2026, leaving 344 unsold.

How much construction of Aaradhya Onepark is complete?

By the developer's own quarterly filing, 43% of the work is done, measured against the project's cost estimate.

Is there any litigation against Aaradhya Onepark?

No litigation is declared on Aaradhya Onepark's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.

More RERA projects in Ghatkopar East