In ExtensionP52100012098Registered Sept 2017Delayed 1462dExtension1 red flag

Aapla Ghar Chakan Talegaon Phase I

A residential / group housing project by Maple Shelters Chakan 1 in bhamboli, Pune.

Data as of Jul 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Jul 2026.

Construction
65%
cost-weighted
Declared completion
Dec 2027
delayed 1462d
Units sold
259 / 272
95% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Maple Shelters Chakan 1 · Partnership
Project type
Residential / Group Housing
Land area
18,929 m² · Permissible built-up (FSI) 33,390 m²
Total units
272 across 8 wings
Estimated cost
₹32.9 Cr
Land ownership
Promoter is the landowner
Application date
29 Jul 2017
Buildings & units

8 wings across 8 buildings

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA0 of 0 proposed0
NA0 of 0 proposed0
NA5 of 5 proposed48
NA10 of 10 proposed96
NA10 of 10 proposed64
NA10 of 10 proposed64
NA0 of 0 proposed0
NA0 of 0 proposed0
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
Sandeep Hardikar and Associates
Structural engineer
Project bank
HDFC BANK
Location

Where it sits

bhamboli, Pune — 410501.

Locality
bhamboli
District
Pune
Authority
PMRDA
Red flags

1 flag on this project

What they are and why they matter — in the full report.

Unlock the 1 red flag on this project, plus the delay analysis and what-to-verify checklist.

Unlock full report — ₹99
Delay analysis & explanations

Why these flags matter

Unlock the delay analysis, sales & construction narrative, and what-to-verify checklist for this project.

Unlock full report — ₹99
Legal & encumbrance

Complaints, litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

Aapla Ghar Chakan Talegaon Phase I: common questions

Is Aapla Ghar Chakan Talegaon Phase I RERA registered?

Yes. Aapla Ghar Chakan Talegaon Phase I is registered with MahaRERA under registration number P52100012098, granted on 1 September 2017. As of July 2026, the registration is active under a MahaRERA extension.

What is the possession date of Aapla Ghar Chakan Talegaon Phase I?

The developer has declared completion by December 2027 in its MahaRERA filing, revised from the original December 2023. The record shows the project running 1462 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of Aapla Ghar Chakan Talegaon Phase I?

Aapla Ghar Chakan Talegaon Phase I is developed by Maple Shelters Chakan 1, the promoter named in its MahaRERA registration.

Where is Aapla Ghar Chakan Talegaon Phase I located?

Aapla Ghar Chakan Talegaon Phase I is in Bhamboli, Pune (PIN 410501), Maharashtra, as declared in its RERA registration.

How many units does Aapla Ghar Chakan Talegaon Phase I have, and how many are sold?

Aapla Ghar Chakan Talegaon Phase I has 272 units on its RERA registration. 259 were reported sold as of July 2026, leaving 13 unsold.

How much construction of Aapla Ghar Chakan Talegaon Phase I is complete?

By the developer's own quarterly filing, 65% of the work is done, measured against the project's cost estimate.

Is there any litigation against Aapla Ghar Chakan Talegaon Phase I?

No litigation is declared on Aapla Ghar Chakan Talegaon Phase I's MahaRERA record as of July 2026. A clean record reflects what was filed, not a legal title check.