In ExtensionP51800030498Registered Aug 2021Delayed 1461dExtensionNo active red flags

93 Palladian

A commercial project by Vijayalaxmi Builders & Contractors in ANDHERI EAST, Mumbai Suburban.

Data as of Sept 2026, from this project's public MahaRERA filing. View on the MahaRERA portal ↗

Overview

Status & progress

Per MahaRERA record as of Sept 2026.

Construction
91%
cost-weighted
Declared completion
Jun 2028
delayed 1461d
Units sold
105 / 119
88% sell-through
Basics

Project basics

As filed with MahaRERA — not analysis, just the record.

Promoter
Vijayalaxmi Builders & Contractors · Partnership
Project type
Commercial
Land area
3,821 m² · Permissible built-up (FSI) 4,888 m²
Total units
119 across 1 wing
Estimated cost
₹29.1 Cr
Land ownership
Promoter is the landowner
Parking
74 four-wheeler · 0 two-wheeler
Application date
17 Jul 2021
Buildings & units

1 wing

Floors and unit counts as filed.

WingFloors sanctionedTotal units
NA10 of 10 proposed119
People on record

Promoter & professionals

Names and registrations as declared — no background analysis.

Architect
RAKESH G. WAGHMARE · W/42/LS
Structural engineer
Sachin Sulkude · LS/S/624
Project bank
HDFC BANK
Location

Where it sits

ANDHERI EAST, Mumbai Suburban — 400093.

Locality
ANDHERI EAST
District
Mumbai Suburban
Authority
Slum Rehabilitation Authority
Red flags

No active red flags

Absence of a flag reflects the record as filed, not an assessment of safety.

Legal & encumbrance

Litigation & charges

Unlock the complaint list with order and warrant detail, plus full encumbrance and litigation detail and the FAQ.

Unlock full report — ₹99

93 Palladian: common questions

Is 93 Palladian RERA registered?

Yes. 93 Palladian is registered with MahaRERA under registration number P51800030498, granted on 25 August 2021. As of September 2026, the registration is active under a MahaRERA extension.

What is the possession date of 93 Palladian?

The developer has declared completion by June 2028 in its MahaRERA filing, revised from the original June 2024. The record shows the project running 1461 days behind its declared schedule. The RERA completion date is the developer's legal commitment; the possession date in your agreement can differ, so check both.

Who is the builder of 93 Palladian?

93 Palladian is developed by Vijayalaxmi Builders & Contractors, the promoter named in its MahaRERA registration.

Where is 93 Palladian located?

93 Palladian is in Andheri East, Mumbai (PIN 400093), Maharashtra, as declared in its RERA registration.

How many units does 93 Palladian have, and how many are sold?

93 Palladian has 119 units on its RERA registration. 112 were reported sold as of September 2026, leaving 7 unsold.

How much construction of 93 Palladian is complete?

By the developer's own quarterly filing, 91% of the work is done, measured against the project's cost estimate.

Is there any litigation against 93 Palladian?

1 litigation case is declared on 93 Palladian's MahaRERA record. The full report lists each case with its court and status.

More RERA projects in Andheri East